| Vendor Request For Proposal (RFP) Solicitation | 24 days? | 1/1/2007 | 2/1/2007 | | |
| Read the note for an explanation of the purpose of this template | 0 days | 1/1/2007 | 1/1/2007 | | |
| RFP Criteria | 2 days? | 1/1/2007 | 1/2/2007 | | |
| Review criteria to determine if formal RFP process is required | 1 day? | 1/1/2007 | 1/1/2007 | 1 | User Team |
| Inform procurement of need to create RFP | 1 day? | 1/2/2007 | 1/2/2007 | 3 | User Team |
| RFP Solicitation Process | 8 days? | 1/3/2007 | 1/12/2007 | | |
| Define Requirements | 4 days? | 1/3/2007 | 1/8/2007 | | |
| Interview users to understand their product and service needs | 1 day? | 1/3/2007 | 1/3/2007 | 4 | User Team |
| Document requirements | 1 day? | 1/4/2007 | 1/4/2007 | 7 | User Team |
| Define criteria for evaluation of the responses | 1 day? | 1/5/2007 | 1/5/2007 | 8 | Evaluation committee |
| Identify the evaluation team | 1 day? | 1/8/2007 | 1/8/2007 | 9 | |
| RFP Creation | 5 days? | 1/3/2007 | 1/9/2007 | | |
| Obtain template from procurement for RFP format | 1 day? | 1/3/2007 | 1/3/2007 | 4 | User Team |
| Draft RFP | 0 days? | 1/5/2007 | 1/5/2007 | 8,12 | Procurement manager,User Team |
| Review RFP with procurement and subject matter experts | 1 day? | 1/5/2007 | 1/8/2007 | 13 | Evaluation committee |
| Refine RFP | 1 day? | 1/8/2007 | 1/9/2007 | 14 | Procurement manager,User Team |
| RFP content ready to release | 0 days | 1/9/2007 | 1/9/2007 | 15 | |
| Market research | 4 days? | 1/5/2007 | 1/10/2007 | | |
| Identify potential companies with appropriate product or service offerings | 1 day? | 1/5/2007 | 1/5/2007 | 8 | Procurement manager,User Team |
| Determine if preliminary request for interest/information is needed | 0 days? | 1/8/2007 | 1/8/2007 | 18 | Procurement manager,User Team |
| Solicit RFI responses (if needed) | 1 day? | 1/8/2007 | 1/9/2007 | 19 | Procurement manager |
| Finalize target companies for RFP | 1 day? | 1/9/2007 | 1/10/2007 | 20 | Evaluation committee |
| RFP Release to industry | 5 days? | 1/8/2007 | 1/12/2007 | | |
| Determine time frames for specific response stages | 1 day? | 1/8/2007 | 1/8/2007 | 9 | Procurement manager,User Team |
| Finalize RFP with time frames and points of contact | 1 day? | 1/9/2007 | 1/9/2007 | 23 | Procurement manager |
| Release RFP to target companies | 1 day? | 1/10/2007 | 1/11/2007 | 21,24 | Procurement manager |
| Conduct RFP Briefing (if required) | 1 day? | 1/11/2007 | 1/12/2007 | 25 | Procurement manager,User Team |
| RFP Solicitation Process COMPLETE | 0 days | 1/12/2007 | 1/12/2007 | 26 | |
| Post-Solicitation Process | 15 days? | 1/12/2007 | 2/1/2007 | | |
| Collect 'intent to bid' responses | 1 day? | 1/12/2007 | 1/15/2007 | 27 | Procurement manager |
| Q&A Process | 4 days? | 1/15/2007 | 1/18/2007 | | |
| Collect questions from bidding companies | 1 day? | 1/15/2007 | 1/16/2007 | 29 | Procurement manager |
| Prepare formal responses to questions | 1 day? | 1/16/2007 | 1/17/2007 | 31 | Procurement manager,User Team |
| Publish responses to all companies that are on the 'intent to bid' list | 1 day? | 1/17/2007 | 1/18/2007 | 32 | Procurement manager |
| Review Proposals | 5 days? | 1/18/2007 | 1/24/2007 | | |
| Perform initial evaluation and clarify concerns | 1 day? | 1/18/2007 | 1/19/2007 | 10,33 | Evaluation committee |
| Evaluate proposals based on established criteria | 1 day? | 1/19/2007 | 1/22/2007 | 35 | Evaluation committee |
| Eliminate offerors that do not meet criteria | 1 day? | 1/22/2007 | 1/23/2007 | 36 | Evaluation committee |
| Prepare for discussions with remaining offerors | 1 day? | 1/23/2007 | 1/24/2007 | 37 | Procurement manager,User Team |
| Face-to-Face Discussions/Negotiations | 3 days? | 1/24/2007 | 1/26/2007 | | |
| Invite finalists to present their solutions | 1 day? | 1/24/2007 | 1/25/2007 | 38 | Procurement manager |
| Analyze the solutions and demonstrations from finalists | 1 day? | 1/25/2007 | 1/26/2007 | 40 | Evaluation committee |
| Selection Decision | 5 days? | 1/26/2007 | 2/1/2007 | | |
| Analyze final proposals | 1 day? | 1/26/2007 | 1/29/2007 | 41 | Evaluation committee |
| Select vendor | 1 day? | 1/29/2007 | 1/30/2007 | 43 | Evaluation committee |
| Award contract | 1 day? | 1/30/2007 | 1/31/2007 | 44 | Procurement manager |
| Debrief unsuccessful offerors | 1 day? | 1/31/2007 | 2/1/2007 | 45 | Procurement manager |
| Post-Solicitation Phase COMPLETE | 0 days | 2/1/2007 | 2/1/2007 | 46 | |
| Vendor Proposal (RFP) Solicitation COMPLETE | 0 days | 2/1/2007 | 2/1/2007 | 47 | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |