| Six Sigma DMAIC Cycle | 23 days? | Mon 01.01.07 | Wed 31.01.07 | | |
| Six Sigma DMAIC Cycle | 23 days? | Mon 01.01.07 | Wed 31.01.07 | | |
| Define Phase | 4 days? | Mon 01.01.07 | Thu 04.01.07 | | |
| Identify customer and CTQ issues | 1 day? | Mon 01.01.07 | Mon 01.01.07 | | Black/Green Belt |
| Develop team charter | 1 day? | Mon 01.01.07 | Mon 01.01.07 | | Team |
| Define process maps | 1 day? | Tue 02.01.07 | Tue 02.01.07 | 3 | Team |
| Map the value stream | 1 day? | Wed 03.01.07 | Wed 03.01.07 | 5 | Team |
| Review deliverables | 1 day? | Thu 04.01.07 | Thu 04.01.07 | 4,6 | Black/Green Belt |
| Tollgate complete | 0 days | Thu 04.01.07 | Thu 04.01.07 | 7 | |
| Measure Phase | 4 days? | Fri 05.01.07 | Wed 10.01.07 | | |
| Select CTQ characteristics | 1 day? | Fri 05.01.07 | Fri 05.01.07 | 8 | Team |
| Define performance standards | 1 day? | Mon 08.01.07 | Mon 08.01.07 | 10 | Team |
| Establish a data collection plan | 1 day? | Tue 09.01.07 | Tue 09.01.07 | 11 | Team |
| Validate MSA, data collection plan, and SOP | 1 day? | Wed 10.01.07 | Wed 10.01.07 | 12 | Black/Green Belt |
| Tollgate Complete | 0 days | Wed 10.01.07 | Wed 10.01.07 | 13 | |
| Analyze Phase | 4 days? | Thu 11.01.07 | Tue 16.01.07 | | |
| Establish process capability | 1 day? | Thu 11.01.07 | Thu 11.01.07 | 14 | Team |
| Define performance objectives | 1 day? | Fri 12.01.07 | Fri 12.01.07 | 16 | Team |
| Identify variation sources | 1 day? | Mon 15.01.07 | Mon 15.01.07 | 17 | Team |
| Review deliverables | 1 day? | Tue 16.01.07 | Tue 16.01.07 | 18 | Black/Green Belt |
| Tollgate Complete | 0 days | Tue 16.01.07 | Tue 16.01.07 | 19 | |
| Improve Phase | 6 days? | Wed 17.01.07 | Wed 24.01.07 | | |
| Screen potential causes | 1 day? | Wed 17.01.07 | Wed 17.01.07 | 20 | Team |
| Discover variable relationships | 1 day? | Thu 18.01.07 | Thu 18.01.07 | 22 | Team |
| Establish operating tolerances | 1 day? | Fri 19.01.07 | Fri 19.01.07 | 23 | Team |
| Develop a preliminary CBA | 1 day? | Mon 22.01.07 | Mon 22.01.07 | 24 | Team |
| Review deliverables | 1 day? | Tue 23.01.07 | Tue 23.01.07 | 25 | Black/Green Belt |
| Deploy implementation plan | 1 day? | Wed 24.01.07 | Wed 24.01.07 | 26 | Team |
| Tollgate Complete | 0 days | Wed 24.01.07 | Wed 24.01.07 | 27 | |
| Control Phase | 5 days? | Thu 25.01.07 | Wed 31.01.07 | | |
| Define and validate measurement system Xs (inputs) | 1 day? | Thu 25.01.07 | Thu 25.01.07 | 28 | Team |
| Determine process capability | 1 day? | Fri 26.01.07 | Fri 26.01.07 | 30 | Team |
| Implement process control | 1 day? | Mon 29.01.07 | Mon 29.01.07 | 31 | Team |
| Review deliverables | 1 day? | Tue 30.01.07 | Tue 30.01.07 | 32 | Black/Green Belt |
| Obtain process owner signoff | 1 day? | Wed 31.01.07 | Wed 31.01.07 | 33 | Black/Green Belt |
| Tollgate complete | 0 days | Wed 31.01.07 | Wed 31.01.07 | 34 | |
| DMAIC Cycle Complete | 0 days | Wed 31.01.07 | Wed 31.01.07 | 35 | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |