-Six Sigma DMAIC Cycle23 days?1/1/20071/31/2007
-Six Sigma DMAIC Cycle23 days?1/1/20071/31/2007
-Define Phase4 days?1/1/20071/4/2007
Identify customer and CTQ issues1 day?1/1/20071/1/2007Black/Green Belt
Develop team charter1 day?1/1/20071/1/2007Team
Define process maps1 day?1/2/20071/2/20073Team
Map the value stream1 day?1/3/20071/3/20075Team
Review deliverables1 day?1/4/20071/4/20074,6Black/Green Belt
Tollgate complete0 days1/4/20071/4/20077
-Measure Phase4 days?1/5/20071/10/2007
Select CTQ characteristics1 day?1/5/20071/5/20078Team
Define performance standards1 day?1/8/20071/8/200710Team
Establish a data collection plan1 day?1/9/20071/9/200711Team
Validate MSA, data collection plan, and SOP1 day?1/10/20071/10/200712Black/Green Belt
Tollgate Complete0 days1/10/20071/10/200713
-Analyze Phase4 days?1/11/20071/16/2007
Establish process capability1 day?1/11/20071/11/200714Team
Define performance objectives1 day?1/12/20071/12/200716Team
Identify variation sources1 day?1/15/20071/15/200717Team
Review deliverables1 day?1/16/20071/16/200718Black/Green Belt
Tollgate Complete0 days1/16/20071/16/200719
-Improve Phase6 days?1/17/20071/24/2007
Screen potential causes1 day?1/17/20071/17/200720Team
Discover variable relationships1 day?1/18/20071/18/200722Team
Establish operating tolerances1 day?1/19/20071/19/200723Team
Develop a preliminary CBA1 day?1/22/20071/22/200724Team
Review deliverables1 day?1/23/20071/23/200725Black/Green Belt
Deploy implementation plan1 day?1/24/20071/24/200726Team
Tollgate Complete0 days1/24/20071/24/200727
-Control Phase5 days?1/25/20071/31/2007
Define and validate measurement system Xs (inputs)1 day?1/25/20071/25/200728Team
Determine process capability1 day?1/26/20071/26/200730Team
Implement process control1 day?1/29/20071/29/200731Team
Review deliverables1 day?1/30/20071/30/200732Black/Green Belt
Obtain process owner signoff1 day?1/31/20071/31/200733Black/Green Belt
Tollgate complete0 days1/31/20071/31/200734
DMAIC Cycle Complete0 days1/31/20071/31/200735
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
Ready













Welcome close

AmiProject is a free online viewer of Microsoft Project files

Having internet browser is enough to open Microsoft Project file!

Sharing project plan is just 2 clicks away!

Learn more about AmiProject

News

Take part in AmiProject Click&View beta testing!

Found a bug? Report a bug!