| Six Sigma DMAIC Cycle | 23 days? | 1/1/2007 | 1/31/2007 | | |
| Six Sigma DMAIC Cycle | 23 days? | 1/1/2007 | 1/31/2007 | | |
| Define Phase | 4 days? | 1/1/2007 | 1/4/2007 | | |
| Identify customer and CTQ issues | 1 day? | 1/1/2007 | 1/1/2007 | | Black/Green Belt |
| Develop team charter | 1 day? | 1/1/2007 | 1/1/2007 | | Team |
| Define process maps | 1 day? | 1/2/2007 | 1/2/2007 | 3 | Team |
| Map the value stream | 1 day? | 1/3/2007 | 1/3/2007 | 5 | Team |
| Review deliverables | 1 day? | 1/4/2007 | 1/4/2007 | 4,6 | Black/Green Belt |
| Tollgate complete | 0 days | 1/4/2007 | 1/4/2007 | 7 | |
| Measure Phase | 4 days? | 1/5/2007 | 1/10/2007 | | |
| Select CTQ characteristics | 1 day? | 1/5/2007 | 1/5/2007 | 8 | Team |
| Define performance standards | 1 day? | 1/8/2007 | 1/8/2007 | 10 | Team |
| Establish a data collection plan | 1 day? | 1/9/2007 | 1/9/2007 | 11 | Team |
| Validate MSA, data collection plan, and SOP | 1 day? | 1/10/2007 | 1/10/2007 | 12 | Black/Green Belt |
| Tollgate Complete | 0 days | 1/10/2007 | 1/10/2007 | 13 | |
| Analyze Phase | 4 days? | 1/11/2007 | 1/16/2007 | | |
| Establish process capability | 1 day? | 1/11/2007 | 1/11/2007 | 14 | Team |
| Define performance objectives | 1 day? | 1/12/2007 | 1/12/2007 | 16 | Team |
| Identify variation sources | 1 day? | 1/15/2007 | 1/15/2007 | 17 | Team |
| Review deliverables | 1 day? | 1/16/2007 | 1/16/2007 | 18 | Black/Green Belt |
| Tollgate Complete | 0 days | 1/16/2007 | 1/16/2007 | 19 | |
| Improve Phase | 6 days? | 1/17/2007 | 1/24/2007 | | |
| Screen potential causes | 1 day? | 1/17/2007 | 1/17/2007 | 20 | Team |
| Discover variable relationships | 1 day? | 1/18/2007 | 1/18/2007 | 22 | Team |
| Establish operating tolerances | 1 day? | 1/19/2007 | 1/19/2007 | 23 | Team |
| Develop a preliminary CBA | 1 day? | 1/22/2007 | 1/22/2007 | 24 | Team |
| Review deliverables | 1 day? | 1/23/2007 | 1/23/2007 | 25 | Black/Green Belt |
| Deploy implementation plan | 1 day? | 1/24/2007 | 1/24/2007 | 26 | Team |
| Tollgate Complete | 0 days | 1/24/2007 | 1/24/2007 | 27 | |
| Control Phase | 5 days? | 1/25/2007 | 1/31/2007 | | |
| Define and validate measurement system Xs (inputs) | 1 day? | 1/25/2007 | 1/25/2007 | 28 | Team |
| Determine process capability | 1 day? | 1/26/2007 | 1/26/2007 | 30 | Team |
| Implement process control | 1 day? | 1/29/2007 | 1/29/2007 | 31 | Team |
| Review deliverables | 1 day? | 1/30/2007 | 1/30/2007 | 32 | Black/Green Belt |
| Obtain process owner signoff | 1 day? | 1/31/2007 | 1/31/2007 | 33 | Black/Green Belt |
| Tollgate complete | 0 days | 1/31/2007 | 1/31/2007 | 34 | |
| DMAIC Cycle Complete | 0 days | 1/31/2007 | 1/31/2007 | 35 | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |