| Security Infrastructure Improvement Plan | 15 days? | Mon 01.01.07 | Fri 19.01.07 | | |
| Read the note for an explanation of the purpose of this template | 0 days | Mon 01.01.07 | Mon 01.01.07 | | |
| Identify needs assessment team | 1 day? | Mon 01.01.07 | Mon 01.01.07 | 1 | |
| Perform Needs Assessment | 3 days? | Tue 02.01.07 | Thu 04.01.07 | | |
| Perform IT-centric need assessment | 1 day? | Tue 02.01.07 | Tue 02.01.07 | 2 | |
| Perform business need assessment | 1 day? | Tue 02.01.07 | Tue 02.01.07 | 2 | |
| Reconcile IT-centric need with business requirements | 1 day? | Wed 03.01.07 | Wed 03.01.07 | 4,5 | |
| Document reconciled requirements and time frame | 1 day? | Thu 04.01.07 | Thu 04.01.07 | 6 | |
| Needs Assessment COMPLETE | 0 days | Thu 04.01.07 | Thu 04.01.07 | 7 | |
| Perform Solution Domain Assessment | 4 days? | Fri 05.01.07 | Wed 10.01.07 | | |
| Assess currently available technologies | 1 day? | Fri 05.01.07 | Fri 05.01.07 | 7 | |
| For each technology identified… | 2 days? | Fri 05.01.07 | Mon 08.01.07 | | |
| Assess how well technology integrates with current infrastructure | 1 day? | Fri 05.01.07 | Fri 05.01.07 | 7 | |
| Assess how well technology fits with current corporate strategies | 1 day? | Mon 08.01.07 | Mon 08.01.07 | 12 | |
| Assess technology maintenance complexity | 1 day? | Mon 08.01.07 | Mon 08.01.07 | 12 | |
| Assess technology flexibility | 1 day? | Mon 08.01.07 | Mon 08.01.07 | 12 | |
| Assess risks associated with this technology | 1 day? | Mon 08.01.07 | Mon 08.01.07 | 12 | |
| Assess skill-set required for this technology | 1 day? | Mon 08.01.07 | Mon 08.01.07 | 12 | |
| Assess the price-points or value provided by this technology | 1 day? | Mon 08.01.07 | Mon 08.01.07 | 12 | |
| Assess the time required to implement this technology into a solution | 1 day? | Mon 08.01.07 | Mon 08.01.07 | 12 | |
| Time Bound "Technology" Research | 0 days | Mon 08.01.07 | Mon 08.01.07 | 12,13,14,15,16,17,18,19 | |
| Solution possibilities (combinations of technologies) | 3 days? | Mon 08.01.07 | Wed 10.01.07 | | |
| Assess how well solutions integrate with current infrastructure | 1 day? | Mon 08.01.07 | Mon 08.01.07 | 12 | |
| Assess how well solutions fit with current corporate strategies | 1 day? | Tue 09.01.07 | Tue 09.01.07 | 22 | |
| Assess solution maintenance complexity | 1 day? | Tue 09.01.07 | Tue 09.01.07 | 22 | |
| Assess solution flexibility | 1 day? | Tue 09.01.07 | Tue 09.01.07 | 22 | |
| Assess risks associated with solutions | 1 day? | Tue 09.01.07 | Tue 09.01.07 | 22 | |
| Assess skill-set required for each solution | 1 day? | Tue 09.01.07 | Tue 09.01.07 | 22 | |
| Assess the price-points or value provided each solution | 1 day? | Tue 09.01.07 | Tue 09.01.07 | 22 | |
| Assess the time required to implement each solution | 1 day? | Tue 09.01.07 | Tue 09.01.07 | 22 | |
| Assess solution staging and technology deployment roadmaps | 1 day? | Wed 10.01.07 | Wed 10.01.07 | 22,23,24,25,26,27,28 | |
| Time Bound "Solution Development" | 0 days | Wed 10.01.07 | Wed 10.01.07 | 30 | |
| Perform Solution Selection | 1 day? | Thu 11.01.07 | Thu 11.01.07 | | |
| Solution comparison and selection | 1 day? | Thu 11.01.07 | Thu 11.01.07 | 20,31 | |
| Solution Selection Complete | 0 days | Thu 11.01.07 | Thu 11.01.07 | 33 | |
| Planning the Solution | 2 days? | Fri 12.01.07 | Mon 15.01.07 | | |
| Prepare the solution development and deployment schedule | 1 day? | Fri 12.01.07 | Fri 12.01.07 | 33 | |
| Prepare the solution training, support, and maintenance plans | 1 day? | Mon 15.01.07 | Mon 15.01.07 | 36 | |
| Prepare solution deployment/migration plan | 1 day? | Mon 15.01.07 | Mon 15.01.07 | 36 | |
| Execute Implementation of the Solution | 3 days? | Mon 15.01.07 | Wed 17.01.07 | | |
| Solution implementation | 1 day? | Mon 15.01.07 | Mon 15.01.07 | 36 | |
| Solution testing | 1 day? | Tue 16.01.07 | Tue 16.01.07 | 37,38,40 | |
| Solution production migration approval | 1 day? | Wed 17.01.07 | Wed 17.01.07 | 41 | |
| Solution Deployment | 2 days? | Thu 18.01.07 | Fri 19.01.07 | | |
| Migration to solution | 1 day? | Thu 18.01.07 | Thu 18.01.07 | 38,42 | |
| Solution acceptance | 1 day? | Fri 19.01.07 | Fri 19.01.07 | 44 | |
| Solution is Deployed and Accepted | 0 days | Fri 19.01.07 | Fri 19.01.07 | 45 | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |