Jan 1, '07Jan 8, '07Jan 15, '07Jan 22, '07Jan 29, '07Feb 5, '07Feb 12, '07Feb 19, '07Feb 26, '07Mar 5, '07Mar 12, '07Mar 19, '07Mar 26, '07Apr 2, '07Apr 9, '07Apr 16, '07Apr 23, '07Apr 30, '07May 7, '07May 14, '07May 21, '07May 28, '07Jun 4, '07Jun 11, '07Jun 18, '07Jun 25, '07Jul 2, '07Jul 9, '07Jul 16, '07Jul 23, '07
TWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTF
Indicators
Name
Duration
Start
Finish
Predecessors
Resource Names
-Residential Construction152 days1/1/20077/31/2007
-Single Family House - Architect Design (3,000 square feet with full basement)152 days1/1/20077/31/2007
-General Conditions21 days1/1/20071/29/2007
Finalize plans and develop estimate with owner, architect20 days1/1/20071/26/2007General contractor,Architect,Owner,Mortgage lender
Sign contract and notice to proceed1 day1/29/20071/29/20073General contractor,Architect,Owner,Mortgage lender
-Apply for Permits1 day1/29/20071/29/2007
Secure foundation permit0 days1/29/20071/29/20074General contractor
Secure framing permit0 days1/29/20071/29/20074General contractor
Secure electrical permit0 days1/29/20071/29/20074General contractor
Secure plumbing permit0 days1/29/20071/29/20074General contractor
Secure HVAC permit0 days1/29/20071/29/20074General contractor
Secure miscellaneous permits0 days1/29/20071/29/20074General contractor
-Site Work3 days1/30/20072/1/2007
Clear and grub lot1 day1/30/20071/30/20076,7,8,9,10,11Site excavation contractor
Install temporary power service1 day1/31/20071/31/200713Electric company
Install underground utilities1 day2/1/20072/1/200714Electric contractor,Plumbing contractor
-Foundation42 days2/2/20074/2/2007
Excavate for foundations3 days2/2/20072/6/200715Site excavation contractor
Form basement walls13 days2/7/20072/23/200717Concrete contractor
Place concrete for foundations & basement walls12 days2/26/20073/13/200718Concrete contractor
Cure basement walls for 7 days7 days3/14/20073/22/200719
Strip basement wall forms2 days3/23/20073/26/200720Concrete contractor
Waterproof/insulate basement walls2 days3/27/20073/28/200721Concrete contractor
Perform foundation inspection1 day3/29/20073/29/200717,22Inspector
Backfill foundation2 days3/30/20074/2/200723Site excavation contractor
-Framing22 days4/3/20075/2/2007
Install 1st floor joists2 days4/3/20074/4/200724Framing contractor
Lay 1st floor decking2 days4/5/20074/6/200726Framing contractor
Frame 1st floor walls4 days4/9/20074/12/200727Framing contractor
Frame 1st floor corners1 day4/13/20074/13/200728Framing contractor
Install 2nd floor joists2 days4/16/20074/17/200729Framing contractor
Frame 2nd floor decking2 days4/18/20074/19/200730Framing contractor
Frame 2nd floor walls3 days4/20/20074/24/200731Framing contractor
Frame 2nd floor corners2 days4/25/20074/26/200732Framing contractor
Complete roof framing3 days4/27/20075/1/200733Framing contractor
Conduct framing inspection1 day5/2/20075/2/200734Inspector
-Dry In22 days5/2/20075/31/2007
Install 1st floor sheathing3 days5/3/20075/7/200735Framing contractor
Install 2nd floor sheathing3 days5/8/20075/10/200737Framing contractor
Install roof decking3 days5/2/20075/4/200734Framing contractor
Install felt, flashing and shingles3 days5/18/20075/22/200748Roofing contractor
Hang 1st floor exterior doors1 day5/23/20075/23/200740Framing contractor
Install 1st floor windows3 days5/24/20075/28/200741Framing contractor
Install 2nd floor windows3 days5/29/20075/31/200742Framing contractor
-Exterior Finishes19 days6/1/20076/27/2007
Complete exterior brick16 days6/1/20076/22/200743Masonry contractor
Complete exterior siding3 days6/25/20076/27/200745Framing contractor
-Utility Rough-Ins and Complete Concrete21 days5/7/20076/4/2007
Rough-in plumbing5 days5/11/20075/17/200738,39Plumbing contractor
Conduct rough-in plumbing inspection1 day5/18/20075/18/200748Inspector
Place concrete for basement floor11 days5/21/20076/4/200749Concrete contractor
Rough-in electrical5 days5/11/20075/17/200738,39Electric contractor
Conduct rough-in electrical inspection1 day5/18/20075/18/200751Inspector
Rough-in HVAC3 days5/21/20075/23/200752Heating and AC contractor
Conduct rough-in HVAC inspection1 day5/24/20075/24/200753Inspector
Rough-in communication - phone, cable, computer, alarm2 days5/7/20075/8/200739Electric contractor
-Interior Finishes30 days6/1/20077/12/2007
-Insulation11 days6/1/20076/15/2007
Place wall insulation - 1st floor1 day6/1/20076/1/200737,38,43,51,53,55Insulation contractor
Place wall insulation - 2nd floor1 day6/4/20076/4/200758Insulation contractor
Place ceiling insulation - 2nd floor1 day6/14/20076/14/200759,66Insulation contractor
Conduct insulation inspection1 day6/15/20076/15/200760Inspector
-Drywall9 days6/4/20076/14/2007
Install drywall - 1st floor walls2 days6/4/20076/5/200758Drywall contractor
Install drywall - 1st floor overhead2 days6/6/20076/7/200763Drywall contractor
Install drywall 2nd floor walls2 days6/8/20076/11/200759,64Drywall contractor
Install drywall 2nd floor overhead2 days6/12/20076/13/200765Drywall contractor
Tape and float 1st floor drywall1 day6/8/20076/8/200764Drywall contractor
Tape and float 2nd floor drywall1 day6/14/20076/14/200766,67Drywall contractor
-Paint and Wallpaper17 days6/11/20077/3/2007
Texture all except entry and kitchen - 1st floor1 day6/11/20076/11/200767Painting contractor
Paint all except entry and kitchen - 1st floor1 day6/12/20076/12/200770Painting contractor
Hang wallpaper entry and kitchen - 1st floor1 day6/13/20076/13/200771Painting contractor
Texture all - 2nd floor1 day6/12/20076/12/200770Painting contractor
Paint all - 2nd floor1 day6/13/20076/13/200773Painting contractor
Paint exterior siding & trim work4 days6/28/20077/3/200746Painting contractor
-Cabinets6 days6/14/20076/21/2007
Install 1st floor - kitchen cabinets2 days6/14/20076/15/200772Finish carpentry contractor
Install 1st floor - master bath and guest cabinets1 day6/18/20076/18/200777Finish carpentry contractor
Install 2nd floor - hall bath and private bath cabinets1 day6/19/20076/19/200778Finish carpentry contractor
Install chair rails, crown moldings, trim2 days6/20/20076/21/200779Finish carpentry contractor
-Finish Plumbing6 days6/18/20076/25/2007
Complete 1st floor - kitchen plumbing1 day6/18/20076/18/200749,77Plumbing contractor
Complete 1st floor - master bath and guest plumbing2 days6/19/20076/20/200778,82Plumbing contractor
Complete 2nd floor - hall bath and private bath plumbing2 days6/21/20076/22/200779,83Plumbing contractor
Conduct finish plumbing inspection1 day6/25/20076/25/200784Inspector
-Finish Electrical3 days6/25/20076/27/2007
Complete 1st floor circuits to service panel1 day6/25/20076/25/200752,84Electric contractor
Complete 2nd floor circuits to service panel1 day6/26/20076/26/200787Electric contractor
Conduct finish electrical inspection1 day6/27/20076/27/200788Inspector
Complete communications wiring - phone, cable, computer, alarm2 days6/26/20076/27/200785Electric contractor
-Finish HVAC3 days6/28/20077/2/2007
Complete 1st floor - zone 1 HVAC1 day6/28/20076/28/200754,90Heating and AC contractor
Complete 2nd floor - zone 2 HVAC1 day6/29/20076/29/200792Heating and AC contractor
Conduct HVAC inspection1 day7/2/20077/2/200793Inspector
-Carpet, Tile and Appliances8 days7/3/20077/12/2007
Tile entry, kitchen and baths3 days7/3/20077/5/200789,94Flooring contractor
Carpet 1st floor2 days7/6/20077/9/200796Flooring contractor
Carpet 2nd floor2 days7/10/20077/11/200797Flooring contractor
Install appliances1 day7/12/20077/12/200798Appliance contractor
-Landscaping and Grounds Work12 days7/4/20077/19/2007
Pour concrete driveway and sidewalks2 days7/4/20077/5/200775Concrete contractor
Install backyard fence2 days7/13/20077/16/200799,101Fencing contractor
Sod and complete plantings - front yard2 days7/17/20077/18/2007102Landscape contractor
Sod and complete plantings - backyard1 day7/19/20077/19/2007103Landscape contractor
-Final Acceptance8 days7/20/20077/31/2007
Complete final inspection for certificate of occupancy1 day7/20/20077/20/200750,61,80,85,89,94,104Inspector
Cleanup for occupancy1 day7/23/20077/23/200799,106Maid service
Perform final walk-through inspection1 day7/24/20077/24/2007107Owner
Complete punch list items5 days7/25/20077/31/2007108General contractor
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
Ready













Welcome close

AmiProject is a free online viewer of Microsoft Project files

Having internet browser is enough to open Microsoft Project file!

Sharing project plan is just 2 clicks away!

Learn more about AmiProject

News

Take part in AmiProject Click&View beta testing!

Found a bug? Report a bug!