| Residential Construction | 152 days | 1/1/2007 | 7/31/2007 | | |
| Single Family House - Architect Design (3,000 square feet with full basement) | 152 days | 1/1/2007 | 7/31/2007 | | |
| General Conditions | 21 days | 1/1/2007 | 1/29/2007 | | |
| Finalize plans and develop estimate with owner, architect | 20 days | 1/1/2007 | 1/26/2007 | | General contractor,Architect,Owner,Mortgage lender |
| Sign contract and notice to proceed | 1 day | 1/29/2007 | 1/29/2007 | 3 | General contractor,Architect,Owner,Mortgage lender |
| Apply for Permits | 1 day | 1/29/2007 | 1/29/2007 | | |
| Secure foundation permit | 0 days | 1/29/2007 | 1/29/2007 | 4 | General contractor |
| Secure framing permit | 0 days | 1/29/2007 | 1/29/2007 | 4 | General contractor |
| Secure electrical permit | 0 days | 1/29/2007 | 1/29/2007 | 4 | General contractor |
| Secure plumbing permit | 0 days | 1/29/2007 | 1/29/2007 | 4 | General contractor |
| Secure HVAC permit | 0 days | 1/29/2007 | 1/29/2007 | 4 | General contractor |
| Secure miscellaneous permits | 0 days | 1/29/2007 | 1/29/2007 | 4 | General contractor |
| Site Work | 3 days | 1/30/2007 | 2/1/2007 | | |
| Clear and grub lot | 1 day | 1/30/2007 | 1/30/2007 | 6,7,8,9,10,11 | Site excavation contractor |
| Install temporary power service | 1 day | 1/31/2007 | 1/31/2007 | 13 | Electric company |
| Install underground utilities | 1 day | 2/1/2007 | 2/1/2007 | 14 | Electric contractor,Plumbing contractor |
| Foundation | 42 days | 2/2/2007 | 4/2/2007 | | |
| Excavate for foundations | 3 days | 2/2/2007 | 2/6/2007 | 15 | Site excavation contractor |
| Form basement walls | 13 days | 2/7/2007 | 2/23/2007 | 17 | Concrete contractor |
| Place concrete for foundations & basement walls | 12 days | 2/26/2007 | 3/13/2007 | 18 | Concrete contractor |
| Cure basement walls for 7 days | 7 days | 3/14/2007 | 3/22/2007 | 19 | |
| Strip basement wall forms | 2 days | 3/23/2007 | 3/26/2007 | 20 | Concrete contractor |
| Waterproof/insulate basement walls | 2 days | 3/27/2007 | 3/28/2007 | 21 | Concrete contractor |
| Perform foundation inspection | 1 day | 3/29/2007 | 3/29/2007 | 17,22 | Inspector |
| Backfill foundation | 2 days | 3/30/2007 | 4/2/2007 | 23 | Site excavation contractor |
| Framing | 22 days | 4/3/2007 | 5/2/2007 | | |
| Install 1st floor joists | 2 days | 4/3/2007 | 4/4/2007 | 24 | Framing contractor |
| Lay 1st floor decking | 2 days | 4/5/2007 | 4/6/2007 | 26 | Framing contractor |
| Frame 1st floor walls | 4 days | 4/9/2007 | 4/12/2007 | 27 | Framing contractor |
| Frame 1st floor corners | 1 day | 4/13/2007 | 4/13/2007 | 28 | Framing contractor |
| Install 2nd floor joists | 2 days | 4/16/2007 | 4/17/2007 | 29 | Framing contractor |
| Frame 2nd floor decking | 2 days | 4/18/2007 | 4/19/2007 | 30 | Framing contractor |
| Frame 2nd floor walls | 3 days | 4/20/2007 | 4/24/2007 | 31 | Framing contractor |
| Frame 2nd floor corners | 2 days | 4/25/2007 | 4/26/2007 | 32 | Framing contractor |
| Complete roof framing | 3 days | 4/27/2007 | 5/1/2007 | 33 | Framing contractor |
| Conduct framing inspection | 1 day | 5/2/2007 | 5/2/2007 | 34 | Inspector |
| Dry In | 22 days | 5/2/2007 | 5/31/2007 | | |
| Install 1st floor sheathing | 3 days | 5/3/2007 | 5/7/2007 | 35 | Framing contractor |
| Install 2nd floor sheathing | 3 days | 5/8/2007 | 5/10/2007 | 37 | Framing contractor |
| Install roof decking | 3 days | 5/2/2007 | 5/4/2007 | 34 | Framing contractor |
| Install felt, flashing and shingles | 3 days | 5/18/2007 | 5/22/2007 | 48 | Roofing contractor |
| Hang 1st floor exterior doors | 1 day | 5/23/2007 | 5/23/2007 | 40 | Framing contractor |
| Install 1st floor windows | 3 days | 5/24/2007 | 5/28/2007 | 41 | Framing contractor |
| Install 2nd floor windows | 3 days | 5/29/2007 | 5/31/2007 | 42 | Framing contractor |
| Exterior Finishes | 19 days | 6/1/2007 | 6/27/2007 | | |
| Complete exterior brick | 16 days | 6/1/2007 | 6/22/2007 | 43 | Masonry contractor |
| Complete exterior siding | 3 days | 6/25/2007 | 6/27/2007 | 45 | Framing contractor |
| Utility Rough-Ins and Complete Concrete | 21 days | 5/7/2007 | 6/4/2007 | | |
| Rough-in plumbing | 5 days | 5/11/2007 | 5/17/2007 | 38,39 | Plumbing contractor |
| Conduct rough-in plumbing inspection | 1 day | 5/18/2007 | 5/18/2007 | 48 | Inspector |
| Place concrete for basement floor | 11 days | 5/21/2007 | 6/4/2007 | 49 | Concrete contractor |
| Rough-in electrical | 5 days | 5/11/2007 | 5/17/2007 | 38,39 | Electric contractor |
| Conduct rough-in electrical inspection | 1 day | 5/18/2007 | 5/18/2007 | 51 | Inspector |
| Rough-in HVAC | 3 days | 5/21/2007 | 5/23/2007 | 52 | Heating and AC contractor |
| Conduct rough-in HVAC inspection | 1 day | 5/24/2007 | 5/24/2007 | 53 | Inspector |
| Rough-in communication - phone, cable, computer, alarm | 2 days | 5/7/2007 | 5/8/2007 | 39 | Electric contractor |
| Interior Finishes | 30 days | 6/1/2007 | 7/12/2007 | | |
| Insulation | 11 days | 6/1/2007 | 6/15/2007 | | |
| Place wall insulation - 1st floor | 1 day | 6/1/2007 | 6/1/2007 | 37,38,43,51,53,55 | Insulation contractor |
| Place wall insulation - 2nd floor | 1 day | 6/4/2007 | 6/4/2007 | 58 | Insulation contractor |
| Place ceiling insulation - 2nd floor | 1 day | 6/14/2007 | 6/14/2007 | 59,66 | Insulation contractor |
| Conduct insulation inspection | 1 day | 6/15/2007 | 6/15/2007 | 60 | Inspector |
| Drywall | 9 days | 6/4/2007 | 6/14/2007 | | |
| Install drywall - 1st floor walls | 2 days | 6/4/2007 | 6/5/2007 | 58 | Drywall contractor |
| Install drywall - 1st floor overhead | 2 days | 6/6/2007 | 6/7/2007 | 63 | Drywall contractor |
| Install drywall 2nd floor walls | 2 days | 6/8/2007 | 6/11/2007 | 59,64 | Drywall contractor |
| Install drywall 2nd floor overhead | 2 days | 6/12/2007 | 6/13/2007 | 65 | Drywall contractor |
| Tape and float 1st floor drywall | 1 day | 6/8/2007 | 6/8/2007 | 64 | Drywall contractor |
| Tape and float 2nd floor drywall | 1 day | 6/14/2007 | 6/14/2007 | 66,67 | Drywall contractor |
| Paint and Wallpaper | 17 days | 6/11/2007 | 7/3/2007 | | |
| Texture all except entry and kitchen - 1st floor | 1 day | 6/11/2007 | 6/11/2007 | 67 | Painting contractor |
| Paint all except entry and kitchen - 1st floor | 1 day | 6/12/2007 | 6/12/2007 | 70 | Painting contractor |
| Hang wallpaper entry and kitchen - 1st floor | 1 day | 6/13/2007 | 6/13/2007 | 71 | Painting contractor |
| Texture all - 2nd floor | 1 day | 6/12/2007 | 6/12/2007 | 70 | Painting contractor |
| Paint all - 2nd floor | 1 day | 6/13/2007 | 6/13/2007 | 73 | Painting contractor |
| Paint exterior siding & trim work | 4 days | 6/28/2007 | 7/3/2007 | 46 | Painting contractor |
| Cabinets | 6 days | 6/14/2007 | 6/21/2007 | | |
| Install 1st floor - kitchen cabinets | 2 days | 6/14/2007 | 6/15/2007 | 72 | Finish carpentry contractor |
| Install 1st floor - master bath and guest cabinets | 1 day | 6/18/2007 | 6/18/2007 | 77 | Finish carpentry contractor |
| Install 2nd floor - hall bath and private bath cabinets | 1 day | 6/19/2007 | 6/19/2007 | 78 | Finish carpentry contractor |
| Install chair rails, crown moldings, trim | 2 days | 6/20/2007 | 6/21/2007 | 79 | Finish carpentry contractor |
| Finish Plumbing | 6 days | 6/18/2007 | 6/25/2007 | | |
| Complete 1st floor - kitchen plumbing | 1 day | 6/18/2007 | 6/18/2007 | 49,77 | Plumbing contractor |
| Complete 1st floor - master bath and guest plumbing | 2 days | 6/19/2007 | 6/20/2007 | 78,82 | Plumbing contractor |
| Complete 2nd floor - hall bath and private bath plumbing | 2 days | 6/21/2007 | 6/22/2007 | 79,83 | Plumbing contractor |
| Conduct finish plumbing inspection | 1 day | 6/25/2007 | 6/25/2007 | 84 | Inspector |
| Finish Electrical | 3 days | 6/25/2007 | 6/27/2007 | | |
| Complete 1st floor circuits to service panel | 1 day | 6/25/2007 | 6/25/2007 | 52,84 | Electric contractor |
| Complete 2nd floor circuits to service panel | 1 day | 6/26/2007 | 6/26/2007 | 87 | Electric contractor |
| Conduct finish electrical inspection | 1 day | 6/27/2007 | 6/27/2007 | 88 | Inspector |
| Complete communications wiring - phone, cable, computer, alarm | 2 days | 6/26/2007 | 6/27/2007 | 85 | Electric contractor |
| Finish HVAC | 3 days | 6/28/2007 | 7/2/2007 | | |
| Complete 1st floor - zone 1 HVAC | 1 day | 6/28/2007 | 6/28/2007 | 54,90 | Heating and AC contractor |
| Complete 2nd floor - zone 2 HVAC | 1 day | 6/29/2007 | 6/29/2007 | 92 | Heating and AC contractor |
| Conduct HVAC inspection | 1 day | 7/2/2007 | 7/2/2007 | 93 | Inspector |
| Carpet, Tile and Appliances | 8 days | 7/3/2007 | 7/12/2007 | | |
| Tile entry, kitchen and baths | 3 days | 7/3/2007 | 7/5/2007 | 89,94 | Flooring contractor |
| Carpet 1st floor | 2 days | 7/6/2007 | 7/9/2007 | 96 | Flooring contractor |
| Carpet 2nd floor | 2 days | 7/10/2007 | 7/11/2007 | 97 | Flooring contractor |
| Install appliances | 1 day | 7/12/2007 | 7/12/2007 | 98 | Appliance contractor |
| Landscaping and Grounds Work | 12 days | 7/4/2007 | 7/19/2007 | | |
| Pour concrete driveway and sidewalks | 2 days | 7/4/2007 | 7/5/2007 | 75 | Concrete contractor |
| Install backyard fence | 2 days | 7/13/2007 | 7/16/2007 | 99,101 | Fencing contractor |
| Sod and complete plantings - front yard | 2 days | 7/17/2007 | 7/18/2007 | 102 | Landscape contractor |
| Sod and complete plantings - backyard | 1 day | 7/19/2007 | 7/19/2007 | 103 | Landscape contractor |
| Final Acceptance | 8 days | 7/20/2007 | 7/31/2007 | | |
| Complete final inspection for certificate of occupancy | 1 day | 7/20/2007 | 7/20/2007 | 50,61,80,85,89,94,104 | Inspector |
| Cleanup for occupancy | 1 day | 7/23/2007 | 7/23/2007 | 99,106 | Maid service |
| Perform final walk-through inspection | 1 day | 7/24/2007 | 7/24/2007 | 107 | Owner |
| Complete punch list items | 5 days | 7/25/2007 | 7/31/2007 | 108 | General contractor |