January 1, '07January 8, '07January 15, '07January 22, '07January 29, '07February 5, '07February 12, '07February 19, '07February 26, '07March 5, '07March 12, '07March 19, '07March 26, '07April 2, '07April 9, '07April 16, '07April 23, '07April 30, '07May 7, '07May 14, '07May 21, '07May 28, '07June 4, '07June 11, '07June 18, '07June 25, '07July 2, '07July 9, '07July 16, '07July 23, '07
FSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTF
Indicators
Task Name
Duration
Start
Finish
Predecessors
Resource Names
-Residential Construction152 daysMon 01.01.07Tue 31.07.07
-Single Family House - Architect Design (3,000 square feet with full basement)152 daysMon 01.01.07Tue 31.07.07
-General Conditions21 daysMon 01.01.07Mon 29.01.07
Finalize plans and develop estimate with owner, architect20 daysMon 01.01.07Fri 26.01.07General contractor,Architect,Owner,Mortgage lender
Sign contract and notice to proceed1 dayMon 29.01.07Mon 29.01.073General contractor,Architect,Owner,Mortgage lender
-Apply for Permits1 dayMon 29.01.07Mon 29.01.07
Secure foundation permit0 daysMon 29.01.07Mon 29.01.074General contractor
Secure framing permit0 daysMon 29.01.07Mon 29.01.074General contractor
Secure electrical permit0 daysMon 29.01.07Mon 29.01.074General contractor
Secure plumbing permit0 daysMon 29.01.07Mon 29.01.074General contractor
Secure HVAC permit0 daysMon 29.01.07Mon 29.01.074General contractor
Secure miscellaneous permits0 daysMon 29.01.07Mon 29.01.074General contractor
-Site Work3 daysTue 30.01.07Thu 01.02.07
Clear and grub lot1 dayTue 30.01.07Tue 30.01.076,7,8,9,10,11Site excavation contractor
Install temporary power service1 dayWed 31.01.07Wed 31.01.0713Electric company
Install underground utilities1 dayThu 01.02.07Thu 01.02.0714Electric contractor,Plumbing contractor
-Foundation42 daysFri 02.02.07Mon 02.04.07
Excavate for foundations3 daysFri 02.02.07Tue 06.02.0715Site excavation contractor
Form basement walls13 daysWed 07.02.07Fri 23.02.0717Concrete contractor
Place concrete for foundations & basement walls12 daysMon 26.02.07Tue 13.03.0718Concrete contractor
Cure basement walls for 7 days7 daysWed 14.03.07Thu 22.03.0719
Strip basement wall forms2 daysFri 23.03.07Mon 26.03.0720Concrete contractor
Waterproof/insulate basement walls2 daysTue 27.03.07Wed 28.03.0721Concrete contractor
Perform foundation inspection1 dayThu 29.03.07Thu 29.03.0717,22Inspector
Backfill foundation2 daysFri 30.03.07Mon 02.04.0723Site excavation contractor
-Framing22 daysTue 03.04.07Wed 02.05.07
Install 1st floor joists2 daysTue 03.04.07Wed 04.04.0724Framing contractor
Lay 1st floor decking2 daysThu 05.04.07Fri 06.04.0726Framing contractor
Frame 1st floor walls4 daysMon 09.04.07Thu 12.04.0727Framing contractor
Frame 1st floor corners1 dayFri 13.04.07Fri 13.04.0728Framing contractor
Install 2nd floor joists2 daysMon 16.04.07Tue 17.04.0729Framing contractor
Frame 2nd floor decking2 daysWed 18.04.07Thu 19.04.0730Framing contractor
Frame 2nd floor walls3 daysFri 20.04.07Tue 24.04.0731Framing contractor
Frame 2nd floor corners2 daysWed 25.04.07Thu 26.04.0732Framing contractor
Complete roof framing3 daysFri 27.04.07Tue 01.05.0733Framing contractor
Conduct framing inspection1 dayWed 02.05.07Wed 02.05.0734Inspector
-Dry In22 daysWed 02.05.07Thu 31.05.07
Install 1st floor sheathing3 daysThu 03.05.07Mon 07.05.0735Framing contractor
Install 2nd floor sheathing3 daysTue 08.05.07Thu 10.05.0737Framing contractor
Install roof decking3 daysWed 02.05.07Fri 04.05.0734Framing contractor
Install felt, flashing and shingles3 daysFri 18.05.07Tue 22.05.0748Roofing contractor
Hang 1st floor exterior doors1 dayWed 23.05.07Wed 23.05.0740Framing contractor
Install 1st floor windows3 daysThu 24.05.07Mon 28.05.0741Framing contractor
Install 2nd floor windows3 daysTue 29.05.07Thu 31.05.0742Framing contractor
-Exterior Finishes19 daysFri 01.06.07Wed 27.06.07
Complete exterior brick16 daysFri 01.06.07Fri 22.06.0743Masonry contractor
Complete exterior siding3 daysMon 25.06.07Wed 27.06.0745Framing contractor
-Utility Rough-Ins and Complete Concrete21 daysMon 07.05.07Mon 04.06.07
Rough-in plumbing5 daysFri 11.05.07Thu 17.05.0738,39Plumbing contractor
Conduct rough-in plumbing inspection1 dayFri 18.05.07Fri 18.05.0748Inspector
Place concrete for basement floor11 daysMon 21.05.07Mon 04.06.0749Concrete contractor
Rough-in electrical5 daysFri 11.05.07Thu 17.05.0738,39Electric contractor
Conduct rough-in electrical inspection1 dayFri 18.05.07Fri 18.05.0751Inspector
Rough-in HVAC3 daysMon 21.05.07Wed 23.05.0752Heating and AC contractor
Conduct rough-in HVAC inspection1 dayThu 24.05.07Thu 24.05.0753Inspector
Rough-in communication - phone, cable, computer, alarm2 daysMon 07.05.07Tue 08.05.0739Electric contractor
-Interior Finishes30 daysFri 01.06.07Thu 12.07.07
-Insulation11 daysFri 01.06.07Fri 15.06.07
Place wall insulation - 1st floor1 dayFri 01.06.07Fri 01.06.0737,38,43,51,53,55Insulation contractor
Place wall insulation - 2nd floor1 dayMon 04.06.07Mon 04.06.0758Insulation contractor
Place ceiling insulation - 2nd floor1 dayThu 14.06.07Thu 14.06.0759,66Insulation contractor
Conduct insulation inspection1 dayFri 15.06.07Fri 15.06.0760Inspector
-Drywall9 daysMon 04.06.07Thu 14.06.07
Install drywall - 1st floor walls2 daysMon 04.06.07Tue 05.06.0758Drywall contractor
Install drywall - 1st floor overhead2 daysWed 06.06.07Thu 07.06.0763Drywall contractor
Install drywall 2nd floor walls2 daysFri 08.06.07Mon 11.06.0759,64Drywall contractor
Install drywall 2nd floor overhead2 daysTue 12.06.07Wed 13.06.0765Drywall contractor
Tape and float 1st floor drywall1 dayFri 08.06.07Fri 08.06.0764Drywall contractor
Tape and float 2nd floor drywall1 dayThu 14.06.07Thu 14.06.0766,67Drywall contractor
-Paint and Wallpaper17 daysMon 11.06.07Tue 03.07.07
Texture all except entry and kitchen - 1st floor1 dayMon 11.06.07Mon 11.06.0767Painting contractor
Paint all except entry and kitchen - 1st floor1 dayTue 12.06.07Tue 12.06.0770Painting contractor
Hang wallpaper entry and kitchen - 1st floor1 dayWed 13.06.07Wed 13.06.0771Painting contractor
Texture all - 2nd floor1 dayTue 12.06.07Tue 12.06.0770Painting contractor
Paint all - 2nd floor1 dayWed 13.06.07Wed 13.06.0773Painting contractor
Paint exterior siding & trim work4 daysThu 28.06.07Tue 03.07.0746Painting contractor
-Cabinets6 daysThu 14.06.07Thu 21.06.07
Install 1st floor - kitchen cabinets2 daysThu 14.06.07Fri 15.06.0772Finish carpentry contractor
Install 1st floor - master bath and guest cabinets1 dayMon 18.06.07Mon 18.06.0777Finish carpentry contractor
Install 2nd floor - hall bath and private bath cabinets1 dayTue 19.06.07Tue 19.06.0778Finish carpentry contractor
Install chair rails, crown moldings, trim2 daysWed 20.06.07Thu 21.06.0779Finish carpentry contractor
-Finish Plumbing6 daysMon 18.06.07Mon 25.06.07
Complete 1st floor - kitchen plumbing1 dayMon 18.06.07Mon 18.06.0749,77Plumbing contractor
Complete 1st floor - master bath and guest plumbing2 daysTue 19.06.07Wed 20.06.0778,82Plumbing contractor
Complete 2nd floor - hall bath and private bath plumbing2 daysThu 21.06.07Fri 22.06.0779,83Plumbing contractor
Conduct finish plumbing inspection1 dayMon 25.06.07Mon 25.06.0784Inspector
-Finish Electrical3 daysMon 25.06.07Wed 27.06.07
Complete 1st floor circuits to service panel1 dayMon 25.06.07Mon 25.06.0752,84Electric contractor
Complete 2nd floor circuits to service panel1 dayTue 26.06.07Tue 26.06.0787Electric contractor
Conduct finish electrical inspection1 dayWed 27.06.07Wed 27.06.0788Inspector
Complete communications wiring - phone, cable, computer, alarm2 daysTue 26.06.07Wed 27.06.0785Electric contractor
-Finish HVAC3 daysThu 28.06.07Mon 02.07.07
Complete 1st floor - zone 1 HVAC1 dayThu 28.06.07Thu 28.06.0754,90Heating and AC contractor
Complete 2nd floor - zone 2 HVAC1 dayFri 29.06.07Fri 29.06.0792Heating and AC contractor
Conduct HVAC inspection1 dayMon 02.07.07Mon 02.07.0793Inspector
-Carpet, Tile and Appliances8 daysTue 03.07.07Thu 12.07.07
Tile entry, kitchen and baths3 daysTue 03.07.07Thu 05.07.0789,94Flooring contractor
Carpet 1st floor2 daysFri 06.07.07Mon 09.07.0796Flooring contractor
Carpet 2nd floor2 daysTue 10.07.07Wed 11.07.0797Flooring contractor
Install appliances1 dayThu 12.07.07Thu 12.07.0798Appliance contractor
-Landscaping and Grounds Work12 daysWed 04.07.07Thu 19.07.07
Pour concrete driveway and sidewalks2 daysWed 04.07.07Thu 05.07.0775Concrete contractor
Install backyard fence2 daysFri 13.07.07Mon 16.07.0799,101Fencing contractor
Sod and complete plantings - front yard2 daysTue 17.07.07Wed 18.07.07102Landscape contractor
Sod and complete plantings - backyard1 dayThu 19.07.07Thu 19.07.07103Landscape contractor
-Final Acceptance8 daysFri 20.07.07Tue 31.07.07
Complete final inspection for certificate of occupancy1 dayFri 20.07.07Fri 20.07.0750,61,80,85,89,94,104Inspector
Cleanup for occupancy1 dayMon 23.07.07Mon 23.07.0799,106Maid service
Perform final walk-through inspection1 dayTue 24.07.07Tue 24.07.07107Owner
Complete punch list items5 daysWed 25.07.07Tue 31.07.07108General contractor
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
Ready













Ad Panel close