| Project Office | 155 days | Mon 01.01.07 | Fri 03.08.07 | | |
| Project Office Template | 155 days | Mon 01.01.07 | Fri 03.08.07 | | |
| Scope | 10 days | Mon 01.01.07 | Fri 12.01.07 | | |
| Determine Project Office scope | 3 days | Mon 01.01.07 | Wed 03.01.07 | | Corporate management,Project Office coordinator |
| Document high-level Project Office requirements including resources | 2 days | Thu 04.01.07 | Fri 05.01.07 | 3 | Corporate management,Project Office coordinator |
| Justify Project Office via business model | 3 days | Mon 08.01.07 | Wed 10.01.07 | 4 | Corporate management,Project Office coordinator |
| Secure executive sponsorship | 2 days | Thu 11.01.07 | Fri 12.01.07 | 5 | Corporate management,Project Office coordinator |
| Scope complete | 0 days | Fri 12.01.07 | Fri 12.01.07 | 6 | |
| Planning | 67 days | Mon 15.01.07 | Tue 17.04.07 | | |
| Analysis/Logistics | 17 days | Mon 15.01.07 | Tue 06.02.07 | | |
| Review Project Office scope documentation | 1 day | Mon 15.01.07 | Mon 15.01.07 | 7 | Project Office coordinator |
| Establish a management framework | 3 days | Tue 16.01.07 | Thu 18.01.07 | 10 | Corporate management,Project Office coordinator |
| Analyze business objectives | 2 days | Fri 19.01.07 | Mon 22.01.07 | 11 | Project Office coordinator |
| Define mission statement | 2 days | Tue 23.01.07 | Wed 24.01.07 | 12 | Project Office coordinator |
| Define goals | 3 days | Thu 25.01.07 | Mon 29.01.07 | 13 | Project Office coordinator |
| Establish communications plan | 1 day | Tue 30.01.07 | Tue 30.01.07 | 14 | Project Office coordinator |
| Secure Project Office core resources | 1 wk | Wed 31.01.07 | Tue 06.02.07 | 15 | Project Office coordinator |
| Logistics complete | 0 days | Tue 06.02.07 | Tue 06.02.07 | 16 | |
| Policies and Procedures | 20 days | Wed 07.02.07 | Tue 06.03.07 | | |
| Define "best of breed" processes | 1 wk | Wed 07.02.07 | Tue 13.02.07 | 16 | Project Office coordinator,Analyst |
| Define "best of breed" tools | 1 wk | Wed 07.02.07 | Tue 13.02.07 | 16 | Project Office coordinator,Analyst |
| Define "best of breed" techniques | 1 wk | Wed 07.02.07 | Tue 13.02.07 | 16 | Project Office coordinator,Analyst |
| Establish resource relationships | 1 wk | Wed 07.02.07 | Tue 13.02.07 | 16 | Project Office coordinator,Analyst |
| Define compliance criteria | 1 wk | Wed 07.02.07 | Tue 13.02.07 | 16 | Project Office coordinator,Analyst |
| Define project test processes | 1 wk | Wed 14.02.07 | Tue 20.02.07 | 19,20,21,22,23 | Project Office coordinator,Analyst |
| Define reporting requirements | 1 wk | Wed 21.02.07 | Tue 27.02.07 | 24 | Project Office coordinator,Analyst |
| Define Project Office priorities | 1 wk | Wed 28.02.07 | Tue 06.03.07 | 25 | Project Office coordinator,Analyst |
| Policies and procedures complete | 0 days | Tue 06.03.07 | Tue 06.03.07 | 26 | |
| Project Standards and Controls | 28 days | Wed 07.03.07 | Fri 13.04.07 | | |
| Define security/roles/responsibilities | 3 days | Wed 07.03.07 | Fri 09.03.07 | 27 | Project Office coordinator,Analyst |
| Define system parameters | 5 days | Mon 12.03.07 | Fri 16.03.07 | 29 | Project Office coordinator,Analyst |
| Create project numbering schema | 2 days | Mon 19.03.07 | Tue 20.03.07 | 30 | Project Office coordinator,Analyst |
| Define financial reporting integration | 1 wk | Wed 21.03.07 | Tue 27.03.07 | 31 | Project Office coordinator,Analyst |
| Identify project categories for template creation | 3 days | Wed 28.03.07 | Fri 30.03.07 | 32 | Project Office coordinator,Analyst |
| Create project templates | 2 wks | Mon 02.04.07 | Fri 13.04.07 | 33 | Developer |
| Project standards and controls complete | 0 days | Fri 13.04.07 | Fri 13.04.07 | 34 | |
| Empower Project Office | 1 day | Mon 16.04.07 | Mon 16.04.07 | 35 | Corporate management,Project Office coordinator |
| Announce Project Office | 4 hrs | Tue 17.04.07 | Tue 17.04.07 | 36 | Corporate management,Project Office coordinator |
| Planning complete | 0 days | Tue 17.04.07 | Tue 17.04.07 | 37 | |
| Initiate Project Office | 28 days | Tue 17.04.07 | Thu 24.05.07 | | |
| Staff Project Office personnel | 1 wk | Tue 17.04.07 | Tue 24.04.07 | 38 | Project Office coordinator |
| Project Office Support for Existing Projects | 12 days | Tue 24.04.07 | Wed 09.05.07 | | |
| Determine existing projects for Project Office | 2 days | Tue 24.04.07 | Thu 26.04.07 | 40 | Project Office coordinator,Project Office staff analyst |
| Audit projects | 1 wk | Thu 26.04.07 | Thu 03.05.07 | 42 | Project Office staff analyst |
| Modify projects for compliance | 3 days | Thu 03.05.07 | Tue 08.05.07 | 43 | Project Office staff analyst |
| Enter projects into Project Office management | 1 day | Tue 08.05.07 | Wed 09.05.07 | 44 | Project Office staff analyst |
| Project Office support for existing projects complete | 0 days | Wed 09.05.07 | Wed 09.05.07 | 45 | |
| Project Office Support for New Projects | 28 days | Tue 17.04.07 | Thu 24.05.07 | | |
| Identify new projects for Project Office | 1 wk | Tue 17.04.07 | Tue 24.04.07 | 38 | Project Office coordinator,Project Office staff analyst |
| Create project using Project Office criteria/templates | 2 wks | Tue 24.04.07 | Tue 08.05.07 | 48 | Project Office staff analyst |
| Establish monitoring criteria | 3 days | Tue 08.05.07 | Fri 11.05.07 | 49 | Project Office staff analyst |
| Establish performance metrics | 4 days | Fri 11.05.07 | Thu 17.05.07 | 50 | Project Office staff analyst |
| Establish budget guidelines | 3 days | Thu 17.05.07 | Tue 22.05.07 | 51 | Project Office staff analyst |
| Enter project into Project Office management | 2 days | Tue 22.05.07 | Thu 24.05.07 | 52 | Project Office staff analyst |
| Project Office support for new projects complete | 0 days | Thu 24.05.07 | Thu 24.05.07 | 53 | |
| Initiate Project Office complete | 0 days | Thu 24.05.07 | Thu 24.05.07 | 46,54 | |
| Management (ongoing) | 26 days | Thu 24.05.07 | Thu 28.06.07 | | |
| Review business priorities applicable to projects | 1 wk | Thu 24.05.07 | Thu 31.05.07 | 55 | Project Office staff analyst |
| Risk Assessment | 10 days | Thu 31.05.07 | Wed 13.06.07 | | |
| Perform risk assessment | 1 wk | Thu 31.05.07 | Thu 07.06.07 | 57 | Project Office staff analyst |
| Evaluate risk assessment against project priorities | 3 days | Thu 07.06.07 | Tue 12.06.07 | 59 | Project Office staff analyst |
| Prepare contingency plans | 1 day | Tue 12.06.07 | Wed 13.06.07 | 60 | Project Office staff analyst |
| Risk assessment complete | 0 days | Wed 13.06.07 | Wed 13.06.07 | 61 | |
| Monitoring | 12 days | Wed 13.06.07 | Thu 28.06.07 | | |
| Prepare project review meeting agenda | 1 day | Wed 13.06.07 | Thu 14.06.07 | 62 | Project Office staff analyst |
| Conduct project review meetings | 4 hrs | Thu 14.06.07 | Thu 14.06.07 | 64 | Project Office staff analyst |
| Create reports for critical issues, budgets, allocating resources, tracking progress, etc. | 2 days | Fri 15.06.07 | Mon 18.06.07 | 65 | Project Office staff analyst |
| Work to mitigate critical issues | 2 days | Tue 19.06.07 | Wed 20.06.07 | 66 | Project Office staff analyst |
| Assist with allocating resources | 2 days | Thu 21.06.07 | Fri 22.06.07 | 67 | Project Office staff analyst |
| Freeze/release project baselines | 2 days | Mon 25.06.07 | Tue 26.06.07 | 68 | Project Office staff analyst |
| Establish change management control | 1 day | Wed 27.06.07 | Wed 27.06.07 | 69 | Project Office staff analyst |
| Freeze/release project budgets | 1 day | Thu 28.06.07 | Thu 28.06.07 | 70 | Project Office staff analyst |
| Monitoring complete | 0 days | Thu 28.06.07 | Thu 28.06.07 | 71 | |
| Historical/Archival | 13 days | Fri 29.06.07 | Tue 17.07.07 | | |
| Establish project archives | 1 wk | Fri 29.06.07 | Thu 05.07.07 | 72 | Project Office coordinator,Project Office staff analyst |
| Establish lessons learned repository | 1 wk | Fri 06.07.07 | Thu 12.07.07 | 74 | Project Office staff analyst |
| Manage project archives | 3 days | Fri 13.07.07 | Tue 17.07.07 | 75 | Project Office staff analyst |
| Historical complete | 0 days | Tue 17.07.07 | Tue 17.07.07 | 76 | |
| Post Implementation Review | 13 days | Wed 18.07.07 | Fri 03.08.07 | | |
| Obtain user feedback | 3 days | Wed 18.07.07 | Fri 20.07.07 | 77 | Project Office coordinator,Project Office staff analyst |
| Evaluate lessons learned | 1 wk | Mon 23.07.07 | Fri 27.07.07 | 79 | Project Office coordinator,Project Office staff analyst |
| Modify Items as necessary | 1 wk | Mon 30.07.07 | Fri 03.08.07 | 80 | Project Office coordinator,Project Office staff analyst |
| Post implementation review complete | 0 days | Fri 03.08.07 | Fri 03.08.07 | 81 | |
| Project Office template complete | 0 days | Fri 03.08.07 | Fri 03.08.07 | 82 | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |