| Office Move | 127 days | Mon 01.01.07 | Tue 26.06.07 | | |
| Office Move | 127 days | Mon 01.01.07 | Tue 26.06.07 | | |
| Two To Six Months Before Moving Day | 77 days | Mon 01.01.07 | Tue 17.04.07 | | |
| Make list of key needs that must be met by new office space | 7 days | Mon 01.01.07 | Tue 09.01.07 | | Chief relocation officer |
| Identify potential office sites | 20 days | Wed 10.01.07 | Tue 06.02.07 | 3 | Chief relocation officer |
| Make final decision on office space | 10 days | Wed 07.02.07 | Tue 20.02.07 | 4 | Chief relocation officer |
| Finalize lease on office space | 10 days | Wed 21.02.07 | Tue 06.03.07 | 5 | Chief relocation officer |
| Identify major tenant improvement needs | 15 days | Wed 07.03.07 | Tue 27.03.07 | 6 | Office manager |
| Obtain estimates from contractors for major tenant improvements | 5 days | Wed 28.03.07 | Tue 03.04.07 | 7 | Office manager |
| Identify costs for new office (chairs, desks, equipment) | 10 days | Wed 21.02.07 | Tue 06.03.07 | 5 | Chief relocation officer |
| Prepare a budget for the move | 10 days | Wed 07.03.07 | Tue 20.03.07 | 9 | Chief relocation officer |
| Select the move day | 1 day | Wed 07.03.07 | Wed 07.03.07 | 6 | Chief relocation officer |
| Hire contractors for major tenant improvements | 5 days | Wed 04.04.07 | Tue 10.04.07 | 8 | Office manager |
| Obtain necessary permits | 5 days | Wed 11.04.07 | Tue 17.04.07 | 12 | Chief relocation officer |
| Evaluate phone system needs | 1 day | Wed 07.03.07 | Wed 07.03.07 | 6 | Telecommunications administrator |
| Order new phone number | 1 day | Wed 07.03.07 | Wed 07.03.07 | 6 | Telecommunications administrator |
| Order new fax number | 1 day | Wed 07.03.07 | Wed 07.03.07 | 6 | Telecommunications administrator |
| Communicate to employees | 1 day | Wed 07.03.07 | Wed 07.03.07 | 6 | Chief relocation officer |
| Phase one closeout | 0 days | Tue 17.04.07 | Tue 17.04.07 | 3,4,5,6,7,8,9,10,11,12,13,14,15,16,17 | |
| One To Two Months Before Moving Day | 28 days | Wed 18.04.07 | Fri 25.05.07 | | |
| Design office space | 23 days | Wed 18.04.07 | Fri 18.05.07 | 18 | Office manager |
| Assign office space | 5 days | Mon 21.05.07 | Fri 25.05.07 | 20 | Office manager |
| Order chairs | 1 day | Mon 21.05.07 | Mon 21.05.07 | 20 | Office manager |
| Order desks | 1 day | Mon 21.05.07 | Mon 21.05.07 | 20 | Office manager |
| Order systems furniture | 1 day | Mon 21.05.07 | Mon 21.05.07 | 20 | Network support manager |
| Order new office equipment | 1 day | Mon 21.05.07 | Mon 21.05.07 | 20 | Office manager |
| Obtain estimates from moving companies | 12 days | Wed 18.04.07 | Thu 03.05.07 | 18 | Chief relocation officer |
| Hire movers | 1 day | Fri 04.05.07 | Fri 04.05.07 | 26 | Chief relocation officer |
| Evaluate server room needs | 2 days | Mon 21.05.07 | Tue 22.05.07 | 20 | Network support manager |
| Evaluate computer networking needs | 2 days | Mon 21.05.07 | Tue 22.05.07 | 20 | Network support manager |
| Order change of address labels for notification | 1 day | Fri 04.05.07 | Fri 04.05.07 | 26 | Mailroom administrator |
| Order new address labels for notification | 1 day | Fri 04.05.07 | Fri 04.05.07 | 26 | Mailroom administrator |
| Obtain estimates from signage companies | 7 days | Fri 04.05.07 | Mon 14.05.07 | 26 | Office manager |
| Order signage for new location | 1 day | Tue 15.05.07 | Tue 15.05.07 | 32 | Office manager |
| Order phone system | 1 day | Mon 21.05.07 | Mon 21.05.07 | 20 | Telecommunications administrator |
| Order phone lines | 1 day | Tue 22.05.07 | Tue 22.05.07 | 34 | Telecommunications administrator |
| Order internet phone lines | 1 day | Tue 22.05.07 | Tue 22.05.07 | 34 | Network support manager |
| Arrange internal maintenance service | 1 day | Tue 15.05.07 | Tue 15.05.07 | 32 | Environmental engineer |
| Arrange external maintenance service | 1 day | Tue 15.05.07 | Tue 15.05.07 | 32 | Environmental engineer |
| Arrange for trash disposal | 1 day | Tue 15.05.07 | Tue 15.05.07 | 32 | Office manager |
| Arrange for cleaning service | 1 day | Tue 15.05.07 | Tue 15.05.07 | 32 | Office manager |
| Arrange for recycling | 1 day | Tue 15.05.07 | Tue 15.05.07 | 32 | Office manager |
| Phase two closeout | 0 days | Fri 25.05.07 | Fri 25.05.07 | 20,21,22,23,24,25,26,27,28,29,30,31,32,33,34,35,36,37,38,39,40,41 | |
| Two To Four Weeks Before Moving Day | 10 days | Mon 28.05.07 | Fri 08.06.07 | | |
| Appraise assets being transferred to new location | 3 days | Mon 28.05.07 | Wed 30.05.07 | 42 | Accounting manager |
| Get business insurance quotes for new space | 6 days | Thu 31.05.07 | Thu 07.06.07 | 44 | Office manager |
| Purchase insurance for new space | 1 day | Fri 08.06.07 | Fri 08.06.07 | 45 | Office manager |
| Order security system | 1 day | Mon 28.05.07 | Mon 28.05.07 | 42 | Office manager |
| Order keys, access cards | 1 day | Mon 28.05.07 | Mon 28.05.07 | 42 | Office manager |
| Arrange for beverage service | 1 day | Mon 28.05.07 | Mon 28.05.07 | 42 | Office manager |
| Send change of address to all vendors | 1 day | Mon 28.05.07 | Mon 28.05.07 | 42 | Mailroom administrator |
| Send change of address to all customers | 1 day | Mon 28.05.07 | Mon 28.05.07 | 42 | Mailroom administrator |
| Send change of address to all subscriptions | 1 day | Mon 28.05.07 | Mon 28.05.07 | 42 | Mailroom administrator |
| Notify all leasers of equipment move | 1 day | Mon 28.05.07 | Mon 28.05.07 | 42 | Office manager |
| Order checks with new address | 1 day | Mon 28.05.07 | Mon 28.05.07 | 42 | Office manager |
| Order long-distance service | 1 day | Mon 28.05.07 | Mon 28.05.07 | 42 | Telecommunications administrator |
| Transfer toll-free numbers or order new numbers | 1 day | Mon 28.05.07 | Mon 28.05.07 | 42 | Telecommunications administrator |
| Plan for disposal of old office equipment | 3 days | Mon 28.05.07 | Wed 30.05.07 | 42 | Office manager |
| Dispose of old office equipment | 1 day | Mon 28.05.07 | Mon 28.05.07 | 42 | Office manager |
| Plan for disposal of old office furniture | 3 days | Mon 28.05.07 | Wed 30.05.07 | 42 | Office manager |
| Dispose of old office furniture | 1 day | Mon 28.05.07 | Mon 28.05.07 | 42 | Office manager |
| Phase three closeout | 0 days | Fri 08.06.07 | Fri 08.06.07 | 44,45,46,47,48,49,50,51,52,53,54,55,56,57,58,59,60 | |
| One Day To Two Weeks Before Moving Day | 10 days | Mon 11.06.07 | Fri 22.06.07 | | |
| Install phone lines | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Local phone company |
| Install phone system | 4 days | Tue 12.06.07 | Fri 15.06.07 | 63 | Telecommunications administrator |
| Assign new phone numbers, extensions | 2 days | Mon 18.06.07 | Tue 19.06.07 | 64 | Telecommunications administrator |
| Order new letterhead and envelopes | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Office manager |
| Order new business cards | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Office manager |
| Order new business forms | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Office manager |
| Schedule disconnection of utilities | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Office manager |
| Repair new office | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Environmental engineer |
| Clean new office | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Cleaning service |
| Identify closest overnight drop off boxes | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Mailroom administrator |
| Inventory existing office furniture (general) | 5 days | Mon 11.06.07 | Fri 15.06.07 | 61 | Office manager |
| Inventory existing computers | 5 days | Mon 11.06.07 | Fri 15.06.07 | 61 | Network support manager |
| Inventory existing furniture by office | 5 days | Mon 11.06.07 | Fri 15.06.07 | 61 | Office manager |
| Shred documents | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Office manager |
| Purge old, obsolete materials | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Office manager |
| Create new office extension directory | 1 day | Wed 20.06.07 | Wed 20.06.07 | 65 | Telecommunications administrator |
| Create new office layout map | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Office manager |
| Create new fax cover sheet | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Office manager |
| Create driving instructions to new location for employees | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Office manager |
| Obtain public transportation information for new location | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Office manager |
| Get shipping labels | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Mailroom administrator |
| Notify post office of change of address | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Mailroom administrator |
| Update company website with new information | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Webmaster |
| Order moving boxes | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Mailroom administrator |
| Pack up desks, personal spaces | 5 days | Mon 11.06.07 | Fri 15.06.07 | 61 | Movers |
| Pack up common areas | 5 days | Mon 11.06.07 | Fri 15.06.07 | 61 | Movers |
| Label all fragile items | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Office manager |
| Take down systems furniture | 2 days | Mon 18.06.07 | Tue 19.06.07 | 87 | Network support manager |
| Store property that will not be moved | 1 day | Mon 18.06.07 | Mon 18.06.07 | 87,88 | Movers |
| Label furniture to be moved | 2 days | Mon 18.06.07 | Tue 19.06.07 | 87,88 | Office manager |
| Move to central location | 1 day | Mon 18.06.07 | Mon 18.06.07 | 87,88 | Office manager |
| Install systems furniture at new location | 3 days | Wed 20.06.07 | Fri 22.06.07 | 90 | Network support manager |
| Install network wiring at new location | 2 days | Mon 11.06.07 | Tue 12.06.07 | 61 | Network support manager |
| Distribute new keys, cards | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Office manager |
| Collect old keys, cards | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Office manager |
| Empty, defrost and clean refrigerator | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Cleaning service |
| Code new office space on a map for movers | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Office manager |
| Create a moving day team to provide direction to movers | 1 day | Mon 11.06.07 | Mon 11.06.07 | 61 | Chief relocation officer |
| Phase four closeout | 0 days | Fri 22.06.07 | Fri 22.06.07 | 63,64,65,66,67,68,69,70,71,72,73,74,75,76,77,78,79,80,81,82,83,84,85,86,87,88,89,90,91,92,93,94,95,96,97,98,99,100 | |
| Moving Day | 1 day | Mon 25.06.07 | Mon 25.06.07 | | |
| Post coded signs in new office for movers | 1 day | Mon 25.06.07 | Mon 25.06.07 | 101 | Office manager |
| Put moving day team in place | 1 day | Mon 25.06.07 | Mon 25.06.07 | 101 | Chief relocation officer |
| Protect main moving paths | 1 day | Mon 25.06.07 | Mon 25.06.07 | 101 | Office manager |
| Move plants and fine art in separate moving van | 1 day | Mon 25.06.07 | Mon 25.06.07 | 101 | Movers |
| Physical move complete | 0 days | Mon 25.06.07 | Mon 25.06.07 | 103,104,105,106 | |
| Post-Move | 1 day | Tue 26.06.07 | Tue 26.06.07 | | |
| Check carefully for any damaged or missing items | 1 day | Tue 26.06.07 | Tue 26.06.07 | 107 | Office manager |
| Schedule phone training | 1 day | Tue 26.06.07 | Tue 26.06.07 | 107 | Telecommunications administrator |
| Schedule security training | 1 day | Tue 26.06.07 | Tue 26.06.07 | 107 | Office manager |
| Schedule fire drill | 1 day | Tue 26.06.07 | Tue 26.06.07 | 107 | Office manager |
| Periodically visit old office to pick up mail | 1 day | Tue 26.06.07 | Tue 26.06.07 | 107 | Mailroom administrator |
| Schedule open house for clients | 1 day | Tue 26.06.07 | Tue 26.06.07 | 107 | Chief relocation officer |
| Office move project complete | 0 days | Tue 26.06.07 | Tue 26.06.07 | 18,42,61,101,107,109,110,111,112,113,114 | |