| Infrastructure Deployment | 142 days | Mon 01.01.07 | Tue 17.07.07 | | |
| Infrastructure Deployment Template | 142 days | Mon 01.01.07 | Tue 17.07.07 | | |
| Scope | 4 days | Mon 01.01.07 | Thu 04.01.07 | | |
| Determine project scope | 1 day | Mon 01.01.07 | Mon 01.01.07 | | Project management |
| Secure project sponsorship | 1 day | Tue 02.01.07 | Tue 02.01.07 | 3 | Project management |
| Define preliminary resources | 1 day | Wed 03.01.07 | Wed 03.01.07 | 4 | Project management |
| Secure core resources | 1 day | Thu 04.01.07 | Thu 04.01.07 | 5 | Project management |
| Scope complete | 0 days | Thu 04.01.07 | Thu 04.01.07 | 6 | |
| Analysis | 30 days | Fri 05.01.07 | Thu 15.02.07 | | |
| Review Current Infrastructure | 5 days | Fri 05.01.07 | Thu 11.01.07 | | |
| Review hardware environment | 5 days | Fri 05.01.07 | Thu 11.01.07 | 7 | Architecture analyst |
| Review software environment | 5 days | Fri 05.01.07 | Thu 11.01.07 | 7 | Architecture analyst |
| Review communications environment | 5 days | Fri 05.01.07 | Thu 11.01.07 | 7 | Architecture analyst |
| Review connectivity LAN/WAN | 5 days | Fri 05.01.07 | Thu 11.01.07 | 7 | Architecture analyst |
| Review support environment | 5 days | Fri 05.01.07 | Thu 11.01.07 | 7 | Architecture analyst |
| Review geographic factors | 5 days | Fri 05.01.07 | Thu 11.01.07 | 7 | Architecture analyst |
| Review current infrastructure complete | 0 days | Thu 11.01.07 | Thu 11.01.07 | 10,11,12,13,14,15 | |
| Review business goals/direction/vision | 10 days | Fri 12.01.07 | Thu 25.01.07 | 16 | Project management |
| Identify Target Areas for Improvement | 5 days | Fri 26.01.07 | Thu 01.02.07 | | |
| Identify hardware improvements | 5 days | Fri 26.01.07 | Thu 01.02.07 | 17 | Architecture analyst |
| Identify software improvements | 5 days | Fri 26.01.07 | Thu 01.02.07 | 17 | Architecture analyst |
| Identify communications considerations | 5 days | Fri 26.01.07 | Thu 01.02.07 | 17 | Architecture analyst |
| Identify connectivity LAN/WAN improvements/issues | 5 days | Fri 26.01.07 | Thu 01.02.07 | 17 | Architecture analyst |
| Identify support environment improvements/additions | 5 days | Fri 26.01.07 | Thu 01.02.07 | 17 | Architecture analyst |
| Identify mitigation of geographic factors | 5 days | Fri 26.01.07 | Thu 01.02.07 | 17 | Architecture analyst |
| Identify target areas for improvement | 0 days | Thu 01.02.07 | Thu 01.02.07 | 19,20,21,22,23,24 | |
| Define system requirements | 5 days | Fri 02.02.07 | Thu 08.02.07 | 25 | Architecture analyst |
| Define target performance metrics | 5 days | Fri 09.02.07 | Thu 15.02.07 | 26 | Architecture analyst |
| Review Current Market Solution Vendors | 5 days | Fri 02.02.07 | Thu 08.02.07 | | |
| Hardware vendors | 5 days | Fri 02.02.07 | Thu 08.02.07 | 25 | Procurement |
| Software vendors | 5 days | Fri 02.02.07 | Thu 08.02.07 | 25 | Procurement |
| Communications vendors | 5 days | Fri 02.02.07 | Thu 08.02.07 | 25 | Procurement |
| Design partners | 5 days | Fri 02.02.07 | Thu 08.02.07 | 25 | Procurement |
| Implementation partners | 5 days | Fri 02.02.07 | Thu 08.02.07 | 25 | Procurement |
| Review current market solution vendors complete | 0 days | Thu 08.02.07 | Thu 08.02.07 | 29,30,31,32,33 | |
| Analysis complete | 0 days | Thu 15.02.07 | Thu 15.02.07 | 27,34 | |
| Design | 27 days | Fri 16.02.07 | Mon 26.03.07 | | |
| Secure necessary architectural resources | 3 days | Fri 16.02.07 | Tue 20.02.07 | 35 | Project management |
| Draft Preliminary Infrastructure Design Documents | 5 days | Wed 21.02.07 | Tue 27.02.07 | | |
| Preliminary hardware design | 5 days | Wed 21.02.07 | Tue 27.02.07 | 37 | Architecture analyst |
| Preliminary software design | 5 days | Wed 21.02.07 | Tue 27.02.07 | 37 | Architecture analyst |
| Preliminary communications design | 5 days | Wed 21.02.07 | Tue 27.02.07 | 37 | Architecture analyst |
| Preliminary connectivity LAN/WAN design | 5 days | Wed 21.02.07 | Tue 27.02.07 | 37 | Architecture analyst |
| Preliminary support environment design | 5 days | Wed 21.02.07 | Tue 27.02.07 | 37 | Architecture analyst |
| Draft preliminary infrastructure design document complete | 0 days | Tue 27.02.07 | Tue 27.02.07 | 39,40,41,42,43 | |
| Review preliminary design documents | 2 days | Wed 28.02.07 | Thu 01.03.07 | 44 | Project management,Management |
| Obtain feedback/input on design | 2 days | Fri 02.03.07 | Mon 05.03.07 | 45 | Project management,Management |
| Develop Detailed Infrastructure Design Documents | 5 days | Tue 06.03.07 | Mon 12.03.07 | | |
| Develop detailed hardware design | 5 days | Tue 06.03.07 | Mon 12.03.07 | 46 | Architecture analyst |
| Develop detailed software design | 5 days | Tue 06.03.07 | Mon 12.03.07 | 46 | Architecture analyst |
| Develop detailed communications design | 5 days | Tue 06.03.07 | Mon 12.03.07 | 46 | Architecture analyst |
| Develop detailed connectivity LAN/WAN design | 5 days | Tue 06.03.07 | Mon 12.03.07 | 46 | Architecture analyst |
| Develop detailed support environment design | 5 days | Tue 06.03.07 | Mon 12.03.07 | 46 | Architecture analyst |
| Develop detailed infrastructure design documents complete | 0 days | Mon 12.03.07 | Mon 12.03.07 | 48,49,50,51,52 | |
| Align long/short term infrastructure design with business goals | 10 days | Tue 13.03.07 | Mon 26.03.07 | 53 | Architecture analyst,Project management |
| Design complete | 0 days | Mon 26.03.07 | Mon 26.03.07 | 54 | |
| Budget | 16 days | Tue 27.03.07 | Tue 17.04.07 | | |
| Develop budget based on detailed infrastructure documents | 5 days | Tue 27.03.07 | Mon 02.04.07 | 55 | Project management |
| Align budget request with business goals | 5 days | Thu 29.03.07 | Thu 05.04.07 | 57-50 % | Project management |
| Align budget request with infrastructure requirements timeline | 5 days | Tue 03.04.07 | Mon 09.04.07 | 58-50 % | Project management |
| Present long/short term budget request | 3 days | Tue 10.04.07 | Thu 12.04.07 | 59 | Project management |
| Secure multi-phase/year funding for key initiatives | 3 days | Fri 13.04.07 | Tue 17.04.07 | 60 | Project management |
| Budget complete | 0 days | Tue 17.04.07 | Tue 17.04.07 | 61 | |
| Finalization/Validation | 18 days | Wed 18.04.07 | Fri 11.05.07 | | |
| Secure resources based upon approved initiatives | 5 days | Wed 18.04.07 | Tue 24.04.07 | 62 | Project management |
| Finalize detailed design based upon budgetary considerations | 2 days | Wed 25.04.07 | Thu 26.04.07 | 64 | Project management |
| Develop detailed implementation strategy | 5 days | Fri 27.04.07 | Thu 03.05.07 | 65 | Deployment resources |
| Validate implementation strategy in test environment | 3 days | Fri 04.05.07 | Tue 08.05.07 | 66 | Deployment resources |
| Review implementation strategy noting other initiatives | 2 days | Wed 09.05.07 | Thu 10.05.07 | 67 | Deployment resources |
| Secure approval to proceed | 4 hrs | Fri 11.05.07 | Fri 11.05.07 | 68 | Project management |
| Finalization/validation complete | 0 days | Fri 11.05.07 | Fri 11.05.07 | 69 | |
| Deployment | 45 days | Fri 11.05.07 | Thu 12.07.07 | | |
| Logistics | 9 days | Fri 11.05.07 | Wed 23.05.07 | | |
| Secure deployment resources | 5 days | Fri 11.05.07 | Fri 18.05.07 | 70 | Project management,Deployment resources |
| Train deployment resources in deployment methodology | 3 days | Fri 18.05.07 | Wed 23.05.07 | 73 | Project management,Deployment resources |
| Logistics complete | 0 days | Wed 23.05.07 | Wed 23.05.07 | 74 | |
| Pilot | 11 days | Wed 23.05.07 | Wed 06.06.07 | | |
| Select infrastructure component to deploy | 1 day | Wed 23.05.07 | Thu 24.05.07 | 75 | Project management,Deployment resources |
| Review deployment team tasks and timeline | 2 days | Thu 24.05.07 | Mon 28.05.07 | 77 | Project management,Deployment resources |
| Communicate impact to community | 2 hrs | Mon 28.05.07 | Mon 28.05.07 | 78 | Project management,Deployment resources |
| Deploy infrastructure component | 3 days | Mon 28.05.07 | Thu 31.05.07 | 79 | Project management,Deployment resources |
| Test infrastructure component | 1 day | Thu 31.05.07 | Fri 01.06.07 | 80 | Project management,Deployment resources |
| Release to production/operations environment | 2 hrs | Fri 01.06.07 | Fri 01.06.07 | 81 | Project management,Deployment resources |
| Obtain feedback | 2 days | Mon 04.06.07 | Tue 05.06.07 | 82 | Project management,Deployment resources |
| Evaluate pilot feedback | 1 day | Wed 06.06.07 | Wed 06.06.07 | 83 | Project management,Deployment resources |
| Pilot complete | 0 days | Wed 06.06.07 | Wed 06.06.07 | 84 | |
| Determine readiness to proceed | 1 day | Thu 07.06.07 | Thu 07.06.07 | 85 | Project management,Management |
| Final Deployment | 25 days | Fri 08.06.07 | Thu 12.07.07 | | |
| Review deployment team tasks and timeline | 5 days | Fri 08.06.07 | Thu 14.06.07 | 86 | Deployment resources |
| Communicate impact to community | 2 hrs | Fri 15.06.07 | Fri 15.06.07 | 88 | Deployment resources |
| Deploy infrastructure components | 10 days | Fri 15.06.07 | Fri 29.06.07 | 89 | Deployment resources |
| Test infrastructure component | 5 days | Fri 29.06.07 | Fri 06.07.07 | 90 | Deployment resources |
| Release to production/operations environment | 1 day | Fri 06.07.07 | Mon 09.07.07 | 91 | Deployment resources |
| Obtain feedback | 3 days | Mon 09.07.07 | Thu 12.07.07 | 92 | Deployment resources |
| Final deployment complete | 0 days | Thu 12.07.07 | Thu 12.07.07 | 93 | |
| Post Implementation Review | 4 days | Thu 12.07.07 | Tue 17.07.07 | | |
| Document lessons learned | 1 day | Thu 12.07.07 | Fri 13.07.07 | 94 | Architecture analyst,Project management,Deployment resources |
| Distribute to team members | 1 day | Fri 13.07.07 | Mon 16.07.07 | 96 | Architecture analyst,Project management,Deployment resources |
| Create software maintenance team | 1 day | Mon 16.07.07 | Tue 17.07.07 | 97 | Architecture analyst,Project management,Deployment resources |
| Post implementation review complete | 0 days | Tue 17.07.07 | Tue 17.07.07 | 98 | |
| Infrastructure deployment template complete | 0 days | Tue 17.07.07 | Tue 17.07.07 | 99 | |