| Infrastructure Deployment | 142 days | 1/1/2007 | 7/17/2007 | | |
| Infrastructure Deployment Template | 142 days | 1/1/2007 | 7/17/2007 | | |
| Scope | 4 days | 1/1/2007 | 1/4/2007 | | |
| Determine project scope | 1 day | 1/1/2007 | 1/1/2007 | | Project management |
| Secure project sponsorship | 1 day | 1/2/2007 | 1/2/2007 | 3 | Project management |
| Define preliminary resources | 1 day | 1/3/2007 | 1/3/2007 | 4 | Project management |
| Secure core resources | 1 day | 1/4/2007 | 1/4/2007 | 5 | Project management |
| Scope complete | 0 days | 1/4/2007 | 1/4/2007 | 6 | |
| Analysis | 30 days | 1/5/2007 | 2/15/2007 | | |
| Review Current Infrastructure | 5 days | 1/5/2007 | 1/11/2007 | | |
| Review hardware environment | 5 days | 1/5/2007 | 1/11/2007 | 7 | Architecture analyst |
| Review software environment | 5 days | 1/5/2007 | 1/11/2007 | 7 | Architecture analyst |
| Review communications environment | 5 days | 1/5/2007 | 1/11/2007 | 7 | Architecture analyst |
| Review connectivity LAN/WAN | 5 days | 1/5/2007 | 1/11/2007 | 7 | Architecture analyst |
| Review support environment | 5 days | 1/5/2007 | 1/11/2007 | 7 | Architecture analyst |
| Review geographic factors | 5 days | 1/5/2007 | 1/11/2007 | 7 | Architecture analyst |
| Review current infrastructure complete | 0 days | 1/11/2007 | 1/11/2007 | 10,11,12,13,14,15 | |
| Review business goals/direction/vision | 10 days | 1/12/2007 | 1/25/2007 | 16 | Project management |
| Identify Target Areas for Improvement | 5 days | 1/26/2007 | 2/1/2007 | | |
| Identify hardware improvements | 5 days | 1/26/2007 | 2/1/2007 | 17 | Architecture analyst |
| Identify software improvements | 5 days | 1/26/2007 | 2/1/2007 | 17 | Architecture analyst |
| Identify communications considerations | 5 days | 1/26/2007 | 2/1/2007 | 17 | Architecture analyst |
| Identify connectivity LAN/WAN improvements/issues | 5 days | 1/26/2007 | 2/1/2007 | 17 | Architecture analyst |
| Identify support environment improvements/additions | 5 days | 1/26/2007 | 2/1/2007 | 17 | Architecture analyst |
| Identify mitigation of geographic factors | 5 days | 1/26/2007 | 2/1/2007 | 17 | Architecture analyst |
| Identify target areas for improvement | 0 days | 2/1/2007 | 2/1/2007 | 19,20,21,22,23,24 | |
| Define system requirements | 5 days | 2/2/2007 | 2/8/2007 | 25 | Architecture analyst |
| Define target performance metrics | 5 days | 2/9/2007 | 2/15/2007 | 26 | Architecture analyst |
| Review Current Market Solution Vendors | 5 days | 2/2/2007 | 2/8/2007 | | |
| Hardware vendors | 5 days | 2/2/2007 | 2/8/2007 | 25 | Procurement |
| Software vendors | 5 days | 2/2/2007 | 2/8/2007 | 25 | Procurement |
| Communications vendors | 5 days | 2/2/2007 | 2/8/2007 | 25 | Procurement |
| Design partners | 5 days | 2/2/2007 | 2/8/2007 | 25 | Procurement |
| Implementation partners | 5 days | 2/2/2007 | 2/8/2007 | 25 | Procurement |
| Review current market solution vendors complete | 0 days | 2/8/2007 | 2/8/2007 | 29,30,31,32,33 | |
| Analysis complete | 0 days | 2/15/2007 | 2/15/2007 | 27,34 | |
| Design | 27 days | 2/16/2007 | 3/26/2007 | | |
| Secure necessary architectural resources | 3 days | 2/16/2007 | 2/20/2007 | 35 | Project management |
| Draft Preliminary Infrastructure Design Documents | 5 days | 2/21/2007 | 2/27/2007 | | |
| Preliminary hardware design | 5 days | 2/21/2007 | 2/27/2007 | 37 | Architecture analyst |
| Preliminary software design | 5 days | 2/21/2007 | 2/27/2007 | 37 | Architecture analyst |
| Preliminary communications design | 5 days | 2/21/2007 | 2/27/2007 | 37 | Architecture analyst |
| Preliminary connectivity LAN/WAN design | 5 days | 2/21/2007 | 2/27/2007 | 37 | Architecture analyst |
| Preliminary support environment design | 5 days | 2/21/2007 | 2/27/2007 | 37 | Architecture analyst |
| Draft preliminary infrastructure design document complete | 0 days | 2/27/2007 | 2/27/2007 | 39,40,41,42,43 | |
| Review preliminary design documents | 2 days | 2/28/2007 | 3/1/2007 | 44 | Project management,Management |
| Obtain feedback/input on design | 2 days | 3/2/2007 | 3/5/2007 | 45 | Project management,Management |
| Develop Detailed Infrastructure Design Documents | 5 days | 3/6/2007 | 3/12/2007 | | |
| Develop detailed hardware design | 5 days | 3/6/2007 | 3/12/2007 | 46 | Architecture analyst |
| Develop detailed software design | 5 days | 3/6/2007 | 3/12/2007 | 46 | Architecture analyst |
| Develop detailed communications design | 5 days | 3/6/2007 | 3/12/2007 | 46 | Architecture analyst |
| Develop detailed connectivity LAN/WAN design | 5 days | 3/6/2007 | 3/12/2007 | 46 | Architecture analyst |
| Develop detailed support environment design | 5 days | 3/6/2007 | 3/12/2007 | 46 | Architecture analyst |
| Develop detailed infrastructure design documents complete | 0 days | 3/12/2007 | 3/12/2007 | 48,49,50,51,52 | |
| Align long/short term infrastructure design with business goals | 10 days | 3/13/2007 | 3/26/2007 | 53 | Architecture analyst,Project management |
| Design complete | 0 days | 3/26/2007 | 3/26/2007 | 54 | |
| Budget | 16 days | 3/27/2007 | 4/17/2007 | | |
| Develop budget based on detailed infrastructure documents | 5 days | 3/27/2007 | 4/2/2007 | 55 | Project management |
| Align budget request with business goals | 5 days | 3/29/2007 | 4/5/2007 | 57-50 % | Project management |
| Align budget request with infrastructure requirements timeline | 5 days | 4/3/2007 | 4/9/2007 | 58-50 % | Project management |
| Present long/short term budget request | 3 days | 4/10/2007 | 4/12/2007 | 59 | Project management |
| Secure multi-phase/year funding for key initiatives | 3 days | 4/13/2007 | 4/17/2007 | 60 | Project management |
| Budget complete | 0 days | 4/17/2007 | 4/17/2007 | 61 | |
| Finalization/Validation | 18 days | 4/18/2007 | 5/11/2007 | | |
| Secure resources based upon approved initiatives | 5 days | 4/18/2007 | 4/24/2007 | 62 | Project management |
| Finalize detailed design based upon budgetary considerations | 2 days | 4/25/2007 | 4/26/2007 | 64 | Project management |
| Develop detailed implementation strategy | 5 days | 4/27/2007 | 5/3/2007 | 65 | Deployment resources |
| Validate implementation strategy in test environment | 3 days | 5/4/2007 | 5/8/2007 | 66 | Deployment resources |
| Review implementation strategy noting other initiatives | 2 days | 5/9/2007 | 5/10/2007 | 67 | Deployment resources |
| Secure approval to proceed | 4 hrs | 5/11/2007 | 5/11/2007 | 68 | Project management |
| Finalization/validation complete | 0 days | 5/11/2007 | 5/11/2007 | 69 | |
| Deployment | 45 days | 5/11/2007 | 7/12/2007 | | |
| Logistics | 9 days | 5/11/2007 | 5/23/2007 | | |
| Secure deployment resources | 5 days | 5/11/2007 | 5/18/2007 | 70 | Project management,Deployment resources |
| Train deployment resources in deployment methodology | 3 days | 5/18/2007 | 5/23/2007 | 73 | Project management,Deployment resources |
| Logistics complete | 0 days | 5/23/2007 | 5/23/2007 | 74 | |
| Pilot | 11 days | 5/23/2007 | 6/6/2007 | | |
| Select infrastructure component to deploy | 1 day | 5/23/2007 | 5/24/2007 | 75 | Project management,Deployment resources |
| Review deployment team tasks and timeline | 2 days | 5/24/2007 | 5/28/2007 | 77 | Project management,Deployment resources |
| Communicate impact to community | 2 hrs | 5/28/2007 | 5/28/2007 | 78 | Project management,Deployment resources |
| Deploy infrastructure component | 3 days | 5/28/2007 | 5/31/2007 | 79 | Project management,Deployment resources |
| Test infrastructure component | 1 day | 5/31/2007 | 6/1/2007 | 80 | Project management,Deployment resources |
| Release to production/operations environment | 2 hrs | 6/1/2007 | 6/1/2007 | 81 | Project management,Deployment resources |
| Obtain feedback | 2 days | 6/4/2007 | 6/5/2007 | 82 | Project management,Deployment resources |
| Evaluate pilot feedback | 1 day | 6/6/2007 | 6/6/2007 | 83 | Project management,Deployment resources |
| Pilot complete | 0 days | 6/6/2007 | 6/6/2007 | 84 | |
| Determine readiness to proceed | 1 day | 6/7/2007 | 6/7/2007 | 85 | Project management,Management |
| Final Deployment | 25 days | 6/8/2007 | 7/12/2007 | | |
| Review deployment team tasks and timeline | 5 days | 6/8/2007 | 6/14/2007 | 86 | Deployment resources |
| Communicate impact to community | 2 hrs | 6/15/2007 | 6/15/2007 | 88 | Deployment resources |
| Deploy infrastructure components | 10 days | 6/15/2007 | 6/29/2007 | 89 | Deployment resources |
| Test infrastructure component | 5 days | 6/29/2007 | 7/6/2007 | 90 | Deployment resources |
| Release to production/operations environment | 1 day | 7/6/2007 | 7/9/2007 | 91 | Deployment resources |
| Obtain feedback | 3 days | 7/9/2007 | 7/12/2007 | 92 | Deployment resources |
| Final deployment complete | 0 days | 7/12/2007 | 7/12/2007 | 93 | |
| Post Implementation Review | 4 days | 7/12/2007 | 7/17/2007 | | |
| Document lessons learned | 1 day | 7/12/2007 | 7/13/2007 | 94 | Architecture analyst,Project management,Deployment resources |
| Distribute to team members | 1 day | 7/13/2007 | 7/16/2007 | 96 | Architecture analyst,Project management,Deployment resources |
| Create software maintenance team | 1 day | 7/16/2007 | 7/17/2007 | 97 | Architecture analyst,Project management,Deployment resources |
| Post implementation review complete | 0 days | 7/17/2007 | 7/17/2007 | 98 | |
| Infrastructure deployment template complete | 0 days | 7/17/2007 | 7/17/2007 | 99 | |