| ISO 9001 Management Review | 11 days? | Mon 01.01.07 | Mon 15.01.07 | | |
| Read the note for an explanation of the purpose of this template | 0 days | Mon 01.01.07 | Mon 01.01.07 | | ISO Management Representative |
| Review Setup | 2 days? | Mon 01.01.07 | Tue 02.01.07 | | |
| Prepare agenda | 1 day? | Mon 01.01.07 | Mon 01.01.07 | 1 | ISO Management Representative |
| Prepare review documentation forms or system | 1 day? | Tue 02.01.07 | Tue 02.01.07 | 3 | ISO Management Representative |
| Management Review Setup COMPLETE | 0 days | Tue 02.01.07 | Tue 02.01.07 | 4 | |
| Compile Inputs for the Review | 5 days? | Wed 03.01.07 | Tue 09.01.07 | | |
| 1. Audit Results | 5 days? | Wed 03.01.07 | Tue 09.01.07 | | |
| Create comparison report for internal audits of the quality management system | 1 day? | Wed 03.01.07 | Wed 03.01.07 | 5 | Quality Assurance Manager |
| Create comparison report for audits performed by an ISO 9000 registrar | 1 day? | Thu 04.01.07 | Thu 04.01.07 | 8 | ISO Management Representative |
| Create comparison report for audits performed by customers | 1 day? | Fri 05.01.07 | Fri 05.01.07 | 9 | Quality Assurance Manager |
| Create comparison report for audits performed by regulatory authorities | 1 day? | Mon 08.01.07 | Mon 08.01.07 | 10 | ISO Management Representative |
| Create comparison report for self-assessment audits performed by individual process owners | 1 day? | Tue 09.01.07 | Tue 09.01.07 | 11 | Quality Assurance Manager |
| Item 1. COMPLETE | 0 days | Tue 09.01.07 | Tue 09.01.07 | 12 | |
| 2. Customer Feedback | 2 days? | Wed 03.01.07 | Thu 04.01.07 | | |
| Compare customer feedback to quality objectives for customer needs and expectations | 1 day? | Wed 03.01.07 | Wed 03.01.07 | 5 | Quality Assurance Manager |
| Produce analysis report | 1 day? | Thu 04.01.07 | Thu 04.01.07 | 15 | Quality Assurance Manager |
| Item 2. COMPLETE | 0 days | Thu 04.01.07 | Thu 04.01.07 | 16 | |
| 3. Product Conformance | 5 days? | Wed 03.01.07 | Tue 09.01.07 | | |
| Analyze product characteristic results | 1 day? | Wed 03.01.07 | Wed 03.01.07 | 5 | Quality Assurance Manager |
| Analyze product use results | 1 day? | Thu 04.01.07 | Thu 04.01.07 | 19 | Quality Assurance Manager |
| Analyze on-time delivery performance | 1 day? | Fri 05.01.07 | Fri 05.01.07 | 20 | Quality Assurance Manager |
| Analyze process performance results | 1 day? | Mon 08.01.07 | Mon 08.01.07 | 21 | Quality Assurance Manager |
| Produce analysis report | 1 day? | Tue 09.01.07 | Tue 09.01.07 | 22 | Quality Assurance Manager |
| Item 3. COMPLETE | 0 days | Tue 09.01.07 | Tue 09.01.07 | 23 | |
| 4. Corrective/Preventative Action Feedback | 3 days? | Wed 03.01.07 | Fri 05.01.07 | | |
| Review time to close corrective/preventative actions | 1 day? | Wed 03.01.07 | Wed 03.01.07 | 5 | Quality Assurance Manager |
| Review degree of reoccurrence | 1 day? | Thu 04.01.07 | Thu 04.01.07 | 26 | Quality Assurance Manager |
| Review method effectiveness | 1 day? | Fri 05.01.07 | Fri 05.01.07 | 27 | Quality Assurance Manager |
| Item 4. COMPLETE | 0 days | Fri 05.01.07 | Fri 05.01.07 | 28 | |
| 5. Prior Management Review Follow-up | 2 days? | Wed 03.01.07 | Thu 04.01.07 | | |
| Prepare report on corrective/preventative action status | 1 day? | Wed 03.01.07 | Wed 03.01.07 | 5 | Quality Assurance Manager |
| Prepare report on status of projects | 1 day? | Thu 04.01.07 | Thu 04.01.07 | 31 | Quality Assurance Manager |
| Item 5. COMPLETE | 0 days | Thu 04.01.07 | Thu 04.01.07 | 32 | |
| 6. Change Assessment | 2 days? | Wed 03.01.07 | Thu 04.01.07 | | |
| Identify any changes in the organization that affect the quality management system | 1 day? | Wed 03.01.07 | Wed 03.01.07 | 5 | Quality Assurance Manager |
| Produce changes documentation | 1 day? | Thu 04.01.07 | Thu 04.01.07 | 35 | Quality Assurance Manager |
| Item 6. COMPLETE | 0 days | Thu 04.01.07 | Thu 04.01.07 | 36 | |
| 7. Improvement Recommendations | 1 day? | Wed 03.01.07 | Wed 03.01.07 | | |
| Identify recommendations to improve effectiveness, innovation, or new marketing opportunities | 1 day? | Wed 03.01.07 | Wed 03.01.07 | 5 | Quality Assurance Manager |
| Item 7. COMPLETE | 0 days | Wed 03.01.07 | Wed 03.01.07 | 39 | |
| Review Inputs COMPLETE | 0 days | Tue 09.01.07 | Tue 09.01.07 | 13,17,24,29,33,37,40 | |
| Conduct Management Review Meeting(s) | 1 day? | Wed 10.01.07 | Wed 10.01.07 | | |
| Review the quality management system | 1 day? | Wed 10.01.07 | Wed 10.01.07 | 41 | Senior Management Team,ISO Management Representative,Quality Assurance Manager |
| Review the quality policy | 1 day? | Wed 10.01.07 | Wed 10.01.07 | 41 | Senior Management Team,ISO Management Representative,Quality Assurance Manager |
| Review the quality objectives | 1 day? | Wed 10.01.07 | Wed 10.01.07 | 41 | Senior Management Team,ISO Management Representative,Quality Assurance Manager |
| Document the Review Proceedings | 1 day? | Wed 10.01.07 | Wed 10.01.07 | | |
| Identify all actions | 1 day? | Wed 10.01.07 | Wed 10.01.07 | 41 | ISO Management Representative |
| Management Review Meeting(s) COMPLETE | 0 days | Wed 10.01.07 | Wed 10.01.07 | 43,44,45,47 | |
| Create Review Output Records | 3 days? | Thu 11.01.07 | Mon 15.01.07 | | |
| Document decisions/actions regarding improvement of the quality management system | 1 day? | Thu 11.01.07 | Thu 11.01.07 | 48 | ISO Management Representative |
| Document decisions/actions regarding improvement of the product/server related to customer requirements | 1 day? | Thu 11.01.07 | Thu 11.01.07 | 48 | ISO Management Representative |
| Document decisions/actions regarding resource needs | 1 day? | Thu 11.01.07 | Thu 11.01.07 | 48 | ISO Management Representative |
| Ensure that management review records comply with ISO 9001, clause 4.2.4 | 1 day? | Fri 12.01.07 | Fri 12.01.07 | 50,51,52 | ISO Management Representative |
| Secure review records | 1 day? | Mon 15.01.07 | Mon 15.01.07 | 53 | ISO Management Representative |
| Create Output Records COMPLETE | 0 days | Mon 15.01.07 | Mon 15.01.07 | 54 | |
| ISO 9001 Management Review Process COMPLETE | 0 days | Mon 15.01.07 | Mon 15.01.07 | 55 | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |