| Human Resources Information System Implementation | 66 days? | Mon 01.01.07 | Mon 02.04.07 | | |
| Business Case for HRIS Implementation Approved by Executive Management | 0 days | Mon 01.01.07 | Mon 01.01.07 | | |
| Analysis and Requirements | 3 days? | Mon 01.01.07 | Wed 03.01.07 | | |
| HR Data Requirements | 3 days? | Mon 01.01.07 | Wed 03.01.07 | | |
| Review Existing Materials | 1 day? | Mon 01.01.07 | Mon 01.01.07 | 1 | Human Resources |
| Conduct User Base Requirements Sessions | 1 day? | Tue 02.01.07 | Tue 02.01.07 | 4 | Human Resources |
| Develop User Needs Assessment and Complete HR Business Process Flow | 1 day? | Wed 03.01.07 | Wed 03.01.07 | 5 | Human Resources |
| HR Data Requirements Assessment Complete | 0 days | Wed 03.01.07 | Wed 03.01.07 | 6 | |
| Technical Infrastructure Requirements | 2 days? | Mon 01.01.07 | Tue 02.01.07 | | |
| Review Current Infrastructure | 1 day? | Mon 01.01.07 | Mon 01.01.07 | 1 | Information Systems |
| Project Future Demand | 1 day? | Tue 02.01.07 | Tue 02.01.07 | 9 | Information Systems |
| Technical Infrastructure Requirements Assessment Complete | 0 days | Tue 02.01.07 | Tue 02.01.07 | 10 | |
| Analysis and Requirements Complete | 0 days | Wed 03.01.07 | Wed 03.01.07 | 6,10 | |
| Assessment of HRIS Solutions | 7 days? | Thu 04.01.07 | Fri 12.01.07 | | |
| Develop RFP | 1 day? | Thu 04.01.07 | Thu 04.01.07 | 12 | Information Systems,Human Resources |
| Determine Weightings to be Given to Responses | 1 day? | Fri 05.01.07 | Fri 05.01.07 | 14 | Information Systems,Human Resources |
| Issue RFP | 1 day? | Mon 08.01.07 | Mon 08.01.07 | 15 | Procurement |
| Evaluate Responses | 1 day? | Tue 09.01.07 | Tue 09.01.07 | 16 | Information Systems,Human Resources |
| Perform Vendor Response/Requirements Gap Analysis | 1 day? | Wed 10.01.07 | Wed 10.01.07 | 17 | Information Systems,Human Resources |
| Invite Top Candidates to Demo | 1 day? | Thu 11.01.07 | Thu 11.01.07 | 18 | Human Resources,Procurement |
| Select Best Fit HRIS Vendor Solution | 1 day? | Fri 12.01.07 | Fri 12.01.07 | 19 | Information Systems,Human Resources |
| Assessment of HRIS Solutions Complete | 0 days | Fri 12.01.07 | Fri 12.01.07 | 20 | |
| Procure HRIS Solution | 1 day? | Mon 15.01.07 | Mon 15.01.07 | 21 | |
| Design HRIS Solution | 13 days? | Tue 16.01.07 | Thu 01.02.07 | | |
| Iteration Planning | 3 days? | Tue 16.01.07 | Thu 18.01.07 | | |
| Conduct User and Team Training | 1 day? | Tue 16.01.07 | Tue 16.01.07 | 22 | Information Systems |
| Define Iterations | 1 day? | Wed 17.01.07 | Wed 17.01.07 | 25 | Information Systems |
| Define Test Approach | 1 day? | Wed 17.01.07 | Wed 17.01.07 | 25 | Information Systems |
| Review and Baseline Iteration Plan | 1 day? | Thu 18.01.07 | Thu 18.01.07 | 26,27 | Information Systems |
| Iteration Planning Complete | 0 days | Thu 18.01.07 | Thu 18.01.07 | 28 | |
| Implementation Prototyping | 4 days? | Wed 17.01.07 | Mon 22.01.07 | | |
| Develop Scenarios | 1 day? | Wed 17.01.07 | Wed 17.01.07 | 25 | Information Systems |
| Map Scenarios to Package Transactions | 1 day? | Thu 18.01.07 | Thu 18.01.07 | 31 | Information Systems |
| Define the Scenario Steps | 1 day? | Thu 18.01.07 | Thu 18.01.07 | 31 | Information Systems |
| Specify and Prototype Reports | 1 day? | Fri 19.01.07 | Fri 19.01.07 | 33 | Information Systems |
| Specify External Interfaces | 1 day? | Thu 18.01.07 | Thu 18.01.07 | 31 | Information Systems |
| Build Package Prototype | 1 day? | Fri 19.01.07 | Fri 19.01.07 | 35 | Information Systems |
| Exercise/Review Package Prototype | 1 day? | Mon 22.01.07 | Mon 22.01.07 | 36 | |
| Implementation Prototyping Complete | 0 days | Mon 22.01.07 | Mon 22.01.07 | 37 | |
| Iteration Consolidation | 2 days? | Tue 23.01.07 | Wed 24.01.07 | | |
| Design Systems and Integration Test Cases | 1 day? | Tue 23.01.07 | Tue 23.01.07 | 38 | Information Systems,Human Resources |
| Confirm Scope of Future Iterations | 1 day? | Wed 24.01.07 | Wed 24.01.07 | 40 | Information Systems,Human Resources |
| Iteration Consolidation Complete | 0 days | Wed 24.01.07 | Wed 24.01.07 | 41 | |
| Data Migration Design | 6 days? | Fri 19.01.07 | Fri 26.01.07 | | |
| Review Data Acquisition Strategy | 1 day? | Fri 19.01.07 | Fri 19.01.07 | 29 | Information Systems |
| Define Data Migration Sources | 1 day? | Mon 22.01.07 | Mon 22.01.07 | 44 | Information Systems |
| Define Data Migration Rules and Logic | 1 day? | Tue 23.01.07 | Tue 23.01.07 | 45 | Information Systems |
| Perform Data Cleanup | 1 day? | Tue 23.01.07 | Tue 23.01.07 | 45 | Information Systems |
| Design Data Migration Transactions | 1 day? | Wed 24.01.07 | Wed 24.01.07 | 45,46 | Information Systems |
| Determine Data Migration Procedures and Controls | 1 day? | Wed 24.01.07 | Wed 24.01.07 | 46 | Information Systems |
| Review and Baseline Conversion Design | 1 day? | Thu 25.01.07 | Thu 25.01.07 | 49 | Information Systems |
| Obtain Signoff of Conversion Design | 1 day? | Fri 26.01.07 | Fri 26.01.07 | 50 | Information Systems,Human Resources |
| Data Migration Design Complete | 0 days | Fri 26.01.07 | Fri 26.01.07 | 51 | |
| Finalize Integration Design Phase | 4 days? | Mon 29.01.07 | Thu 01.02.07 | | |
| Develop Requirements Traceability Matrix | 1 day? | Mon 29.01.07 | Mon 29.01.07 | 52 | Information Systems |
| Baseline Project/Deliverables | 1 day? | Tue 30.01.07 | Tue 30.01.07 | 54 | Information Systems |
| Develop Schedule for Next Stage | 1 day? | Wed 31.01.07 | Wed 31.01.07 | 55 | Information Systems,Human Resources |
| Review Project Status with Project Board | 1 day? | Thu 01.02.07 | Thu 01.02.07 | 56 | Executive Management,Information Systems,Human Resources |
| Finalize Integration Design Phase Complete | 0 days | Thu 01.02.07 | Thu 01.02.07 | 57 | |
| Integration Design Complete | 0 days | Thu 01.02.07 | Thu 01.02.07 | 58 | |
| Integration, Build, Test | 25 days? | Fri 02.02.07 | Thu 08.03.07 | | |
| Build Iteration Planning | 3 days? | Fri 02.02.07 | Tue 06.02.07 | | |
| Confirm Technical Architecture | 1 day? | Fri 02.02.07 | Fri 02.02.07 | 59 | Information Systems |
| Define Iterations and Builds | 1 day? | Mon 05.02.07 | Mon 05.02.07 | 62 | Information Systems |
| Refine Test Cases | 1 day? | Tue 06.02.07 | Tue 06.02.07 | 63 | Information Systems,Human Resources |
| Build Iteration Planning Complete | 0 days | Tue 06.02.07 | Tue 06.02.07 | 64 | |
| Integration Build | 5 days? | Wed 07.02.07 | Tue 13.02.07 | | |
| Build Reports | 1 day? | Wed 07.02.07 | Wed 07.02.07 | 65 | Information Systems |
| Design and Build Migration Components | 1 day? | Thu 08.02.07 | Thu 08.02.07 | 67 | Information Systems |
| Design and Build External Interfaces | 1 day? | Fri 09.02.07 | Fri 09.02.07 | 68 | Information Systems |
| Optimize Performance | 1 day? | Fri 09.02.07 | Fri 09.02.07 | 68 | Information Systems |
| Complete Unit/Integration Testing | 1 day? | Thu 08.02.07 | Fri 09.02.07 | | Information Systems |
| Review and Baseline Build | 1 day? | Fri 09.02.07 | Mon 12.02.07 | 71 | Information Systems |
| Deliver Build for Testing | 1 day? | Mon 12.02.07 | Tue 13.02.07 | 72 | Information Systems |
| Integration Build Complete | 0 days | Tue 13.02.07 | Tue 13.02.07 | 73 | |
| System Test Design and Development | 3 days? | Tue 13.02.07 | Thu 15.02.07 | | |
| Define Test Scripts | 1 day? | Tue 13.02.07 | Wed 14.02.07 | 74 | Information Systems |
| Review Test Case/Requirement Coverage | 1 day? | Wed 14.02.07 | Thu 15.02.07 | 76 | Information Systems |
| Develop Automated Scripts | 1 day? | Tue 13.02.07 | Wed 14.02.07 | | Information Systems |
| Establish External Test Data Sets | 1 day? | Wed 14.02.07 | Thu 15.02.07 | 76 | Information Systems |
| System Test Design and Development Complete | 0 days | Thu 15.02.07 | Thu 15.02.07 | 79 | |
| System Test Execution | 4 days? | Thu 15.02.07 | Tue 20.02.07 | | |
| Execute Tests and Log Results | 1 day? | Thu 15.02.07 | Fri 16.02.07 | 80 | Information Systems |
| Investigate Unexpected Results | 1 day? | Fri 16.02.07 | Mon 19.02.07 | 82 | Information Systems |
| Estimate, Prioritize, and Schedule Testing Changes | 1 day? | Mon 19.02.07 | Tue 20.02.07 | 83 | Information Systems |
| System Test Execution Complete | 0 days | Tue 20.02.07 | Tue 20.02.07 | 84 | |
| Iteration Review | 3 days? | Tue 20.02.07 | Thu 22.02.07 | | |
| Review System Test Results for Current Iteration | 1 day? | Tue 20.02.07 | Wed 21.02.07 | 85 | Information Systems,Human Resources |
| Confirm Scope of Future Iterations | 1 day? | Wed 21.02.07 | Thu 22.02.07 | 87 | Information Systems,Human Resources |
| Iteration Review Complete | 0 days | Thu 22.02.07 | Thu 22.02.07 | 88 | |
| Acceptance Testing | 7 days? | Thu 22.02.07 | Fri 02.03.07 | | |
| Set Up Acceptance Test Environment | 1 day? | Thu 22.02.07 | Fri 23.02.07 | 89 | Information Systems |
| Create Acceptance Test Scripts | 1 day? | Fri 23.02.07 | Mon 26.02.07 | 91 | Information Systems,Human Resources |
| Execute Acceptance Tests and Log Results | 1 day? | Mon 26.02.07 | Tue 27.02.07 | 92 | Information Systems,Human Resources |
| Update System Based on Acceptance Test Results | 1 day? | Tue 27.02.07 | Wed 28.02.07 | 93 | Information Systems,Human Resources |
| Re-Execute Acceptance Tests and Log Results | 1 day? | Wed 28.02.07 | Thu 01.03.07 | 94 | Information Systems,Human Resources |
| Obtain Signoff of System | 1 day? | Thu 01.03.07 | Fri 02.03.07 | 95 | Information Systems,Human Resources |
| Acceptance Testing Complete | 0 days | Fri 02.03.07 | Fri 02.03.07 | 96 | |
| Package Implementation Complete | 0 days | Fri 02.03.07 | Fri 02.03.07 | 96 | |
| Finalize Integration Phase | 5 days? | Fri 02.03.07 | Thu 08.03.07 | | |
| Develop Requirements Traceability Matrix | 1 day? | Fri 02.03.07 | Mon 05.03.07 | 98 | Information Systems,Human Resources |
| Baseline Project/Deliverables | 1 day? | Mon 05.03.07 | Tue 06.03.07 | 100 | Information Systems,Human Resources |
| Develop Schedule for Next Stage | 1 day? | Tue 06.03.07 | Wed 07.03.07 | 101 | Information Systems,Human Resources |
| Review Project Status with Project Board | 1 day? | Wed 07.03.07 | Thu 08.03.07 | 102 | Human Resources |
| Finalize Integration Phase Complete | 0 days | Thu 08.03.07 | Thu 08.03.07 | 103 | |
| Deploy | 18 days? | Thu 08.03.07 | Mon 02.04.07 | | |
| Education Development | 5 days? | Thu 08.03.07 | Wed 14.03.07 | | |
| Set Up Training Environment | 1 day? | Thu 08.03.07 | Fri 09.03.07 | 104 | Information Systems |
| Create Application User Guide | 1 day? | Fri 09.03.07 | Mon 12.03.07 | 107 | Information Systems,Human Resources |
| Create Administrators Guide | 1 day? | Mon 12.03.07 | Tue 13.03.07 | 108 | Information Systems,Human Resources |
| Develop Training Materials | 1 day? | Tue 13.03.07 | Wed 14.03.07 | 109 | Information Systems,Human Resources |
| Education Development Complete | 0 days | Wed 14.03.07 | Wed 14.03.07 | 110 | |
| Deployment Preparation | 7 days? | Wed 14.03.07 | Thu 22.03.07 | | |
| Develop Background Scheduling Processes | 1 day? | Wed 14.03.07 | Thu 15.03.07 | 111 | Information Systems |
| Create Production Test Scripts | 1 day? | Thu 15.03.07 | Fri 16.03.07 | 113 | Information Systems |
| Review and Compile Technical Implementation Plan | 1 day? | Fri 16.03.07 | Mon 19.03.07 | 113,114 | Information Systems |
| Establish Technical Environment | 1 day? | Mon 19.03.07 | Tue 20.03.07 | 115 | Information Systems |
| Conduct Deployment Briefings | 1 day? | Tue 20.03.07 | Wed 21.03.07 | 116 | Information Systems |
| Conduct Training | 1 day? | Wed 21.03.07 | Thu 22.03.07 | 117 | Human Resources |
| Complete Process Review | 1 day? | Wed 21.03.07 | Thu 22.03.07 | 117 | |
| Deployment Preparation Complete | 0 days | Thu 22.03.07 | Thu 22.03.07 | 119 | |
| Installation and Handover | 6 days? | Thu 22.03.07 | Thu 29.03.07 | | |
| Install Application Software | 1 day? | Thu 22.03.07 | Fri 23.03.07 | 120 | Information Systems |
| Convert Static and Acquire New Data | 1 day? | Fri 23.03.07 | Mon 26.03.07 | 122 | Information Systems |
| Convert Dynamic Data | 1 day? | Fri 23.03.07 | Mon 26.03.07 | 122 | Information Systems |
| Perform Production Tests | 1 day? | Mon 26.03.07 | Tue 27.03.07 | 123,124 | Information Systems |
| Cut Over to New Application | 1 day? | Tue 27.03.07 | Wed 28.03.07 | 125 | Information Systems |
| Create Maintenance Guide | 1 day? | Wed 28.03.07 | Thu 29.03.07 | 126 | |
| Installation and Handover Complete | 0 days | Thu 29.03.07 | Thu 29.03.07 | 127 | |
| Finalize Deployment Phase | 3 days? | Thu 29.03.07 | Mon 02.04.07 | | |
| Perform Lessons Learned Meeting | 1 day? | Thu 29.03.07 | Fri 30.03.07 | 128 | Information Systems,Human Resources |
| Close Project File | 1 day? | Fri 30.03.07 | Mon 02.04.07 | 130 | Information Systems,Human Resources |
| Finalize Deployment Phase Complete | 0 days | Mon 02.04.07 | Mon 02.04.07 | 131 | |
| Deployment Complete | 0 days | Mon 02.04.07 | Mon 02.04.07 | 131 | |
| HRIS Implementation Complete | 0 days | Mon 02.04.07 | Mon 02.04.07 | 133 | |