| Finance and Accounting System Implementation | 73 days? | Mon 01.01.07 | Wed 11.04.07 | | |
| New Finance and Accounting System chosen | 0 days | Mon 01.01.07 | Mon 01.01.07 | | |
| Implementation Requirements | 19 days? | Mon 01.01.07 | Thu 25.01.07 | | |
| Package Architecture Validation | 5 days? | Mon 01.01.07 | Fri 05.01.07 | | |
| Review technical architecture | 1 day? | Mon 01.01.07 | Mon 01.01.07 | 1 | Information Systems |
| Determine package implementation environment | 1 day? | Tue 02.01.07 | Tue 02.01.07 | 4 | Information Systems |
| Provide initial training | 1 day? | Tue 02.01.07 | Tue 02.01.07 | 4 | Information Systems |
| Install the package | 1 day? | Wed 03.01.07 | Wed 03.01.07 | 5 | Information Systems |
| Estimate usage volumes and scaling options | 1 day? | Thu 04.01.07 | Thu 04.01.07 | 7 | Information Systems |
| Ensure that installation is architected for high availability | 1 day? | Thu 04.01.07 | Thu 04.01.07 | 7 | Information Systems |
| Review and baseline technical architecture model | 1 day? | Fri 05.01.07 | Fri 05.01.07 | 9 | Information Systems |
| Package architecture validation complete | 0 days | Fri 05.01.07 | Fri 05.01.07 | 10 | |
| Package and Requirements Review | 2 days? | Thu 04.01.07 | Fri 05.01.07 | | |
| Explore the package | 0 days? | Thu 04.01.07 | Thu 04.01.07 | 7 | Information Systems,Accounting |
| Validate business requirements model | 0 days? | Thu 04.01.07 | Thu 04.01.07 | 13 | Information Systems,Accounting |
| Map business requirements to package | 0 days? | Fri 05.01.07 | Fri 05.01.07 | 14 | Information Systems,Accounting |
| Compile package gap document and identify gap solutions | 0 days? | Fri 05.01.07 | Fri 05.01.07 | 15 | Information Systems,Accounting |
| Package and requirements review complete | 0 days | Fri 05.01.07 | Fri 05.01.07 | 16 | |
| Implementation Options | 5 days? | Mon 08.01.07 | Fri 12.01.07 | | |
| Identify business process options | 0 days? | Mon 08.01.07 | Mon 08.01.07 | 17 | Information Systems,Accounting |
| Evaluate data migration strategies | 1 day? | Mon 08.01.07 | Tue 09.01.07 | 19 | Information Systems |
| Evaluate deployment approach | 1 day? | Mon 08.01.07 | Tue 09.01.07 | 19 | Information Systems |
| Evaluate systems interfaces | 1 day? | Mon 08.01.07 | Tue 09.01.07 | 19 | Information Systems |
| Evaluate delivery increment options | 1 day? | Mon 08.01.07 | Tue 09.01.07 | 19 | Information Systems |
| Document implementation options | 1 day? | Tue 09.01.07 | Wed 10.01.07 | 19,20,21,22,23 | Information Systems |
| Select implementation option | 1 day? | Wed 10.01.07 | Thu 11.01.07 | 24 | Information Systems |
| Develop test and user acceptance plans | 0 days? | Thu 11.01.07 | Thu 11.01.07 | 25 | Information Systems,Accounting |
| Obtain signoff of business process option recommendation | 1 day? | Fri 12.01.07 | Fri 12.01.07 | 26 | Executive Management,Information Systems,Accounting |
| Implementation options complete | 0 days | Fri 12.01.07 | Fri 12.01.07 | 27 | |
| Package Business Increment Design | 5 days? | Mon 15.01.07 | Fri 19.01.07 | | |
| Define implementation increments | 1 day? | Mon 15.01.07 | Mon 15.01.07 | 28 | Information Systems |
| Define increment acceptance criteria | 1 day? | Tue 16.01.07 | Tue 16.01.07 | 30 | Information Systems |
| Define training approach and plan | 1 day? | Wed 17.01.07 | Wed 17.01.07 | 31 | Information Systems |
| Compile delivery increments plan | 1 day? | Thu 18.01.07 | Thu 18.01.07 | 32 | Information Systems |
| Review delivery increments plan | 1 day? | Fri 19.01.07 | Fri 19.01.07 | 33 | Accounting |
| Business implementation design complete | 0 days | Fri 19.01.07 | Fri 19.01.07 | 34 | |
| Finalize Requirements Phase | 4 days? | Mon 22.01.07 | Thu 25.01.07 | | |
| Develop requirements traceability matrix | 1 day? | Mon 22.01.07 | Mon 22.01.07 | 35 | Information Systems |
| Baseline project/deliverables | 1 day? | Tue 23.01.07 | Tue 23.01.07 | 37 | Information Systems |
| Develop schedule for next stage | 1 day? | Wed 24.01.07 | Wed 24.01.07 | 38 | Information Systems |
| Review project status with project board | 0 days? | Thu 25.01.07 | Thu 25.01.07 | 39 | Executive Management,Information Systems,Accounting |
| Requirements phase complete | 0 days | Thu 25.01.07 | Thu 25.01.07 | 40 | |
| Package Integration Design | 14 days? | Thu 25.01.07 | Tue 13.02.07 | | |
| Package Iteration Planning | 4 days? | Thu 25.01.07 | Tue 30.01.07 | | |
| Conduct user and team training | 1 day? | Thu 25.01.07 | Fri 26.01.07 | 41 | Information Systems |
| Define iterations | 1 day? | Fri 26.01.07 | Mon 29.01.07 | 44 | Information Systems |
| Define test approach | 1 day? | Thu 25.01.07 | Fri 26.01.07 | | Information Systems |
| Review and baseline iteration plan | 1 day? | Mon 29.01.07 | Tue 30.01.07 | 45,46 | Information Systems |
| Package Implementation Prototyping | 4 days? | Fri 26.01.07 | Wed 31.01.07 | | |
| Develop scenarios | 1 day? | Fri 26.01.07 | Mon 29.01.07 | 44 | Information Systems |
| Map scenarios to package transactions | 1 day? | Fri 26.01.07 | Mon 29.01.07 | | Information Systems |
| Define the scenario steps | 1 day? | Fri 26.01.07 | Mon 29.01.07 | | Information Systems |
| Specify and prototype reports | 1 day? | Mon 29.01.07 | Tue 30.01.07 | | Information Systems |
| Specify external interfaces | 1 day? | Fri 26.01.07 | Mon 29.01.07 | | Information Systems |
| Build package prototype | 1 day? | Mon 29.01.07 | Tue 30.01.07 | 53 | Information Systems |
| Exercise/review package prototype | 1 day? | Tue 30.01.07 | Wed 31.01.07 | 54 | |
| Package Iteration Consolidation | 2 days? | Wed 31.01.07 | Thu 01.02.07 | | |
| Design systems and integration test cases | 0 days? | Wed 31.01.07 | Thu 01.02.07 | 55 | Information Systems,Accounting |
| Confirm scope of future iterations | 0 days? | Thu 01.02.07 | Thu 01.02.07 | 57 | Information Systems,Accounting |
| Data Migration Design | 7 days? | Tue 30.01.07 | Wed 07.02.07 | | |
| Review data acquisition strategy | 1 day? | Tue 30.01.07 | Wed 31.01.07 | 47 | Information Systems |
| Define data migration sources | 1 day? | Wed 31.01.07 | Thu 01.02.07 | 60 | Information Systems |
| Define data migration rules and logic | 1 day? | Thu 01.02.07 | Fri 02.02.07 | 61 | Information Systems |
| Perform data cleanup | 1 day? | Thu 01.02.07 | Fri 02.02.07 | 61 | Information Systems |
| Design data migration transactions | 1 day? | Fri 02.02.07 | Mon 05.02.07 | 61,62 | Information Systems |
| Determine data migration procedures and controls | 1 day? | Fri 02.02.07 | Mon 05.02.07 | 62 | Information Systems |
| Review and baseline conversion design | 1 day? | Mon 05.02.07 | Tue 06.02.07 | 65 | Information Systems |
| Obtain signoff of conversion design | 1 day? | Tue 06.02.07 | Wed 07.02.07 | 66 | Information Systems,Accounting |
| Finalize Integration Design Phase | 5 days? | Wed 07.02.07 | Tue 13.02.07 | | |
| Develop requirements traceability matrix | 1 day? | Wed 07.02.07 | Thu 08.02.07 | 67 | Information Systems |
| Baseline project/deliverables | 1 day? | Thu 08.02.07 | Fri 09.02.07 | 69 | Information Systems |
| Develop schedule for next stage | 1 day? | Fri 09.02.07 | Mon 12.02.07 | 70 | Information Systems,Accounting |
| Review project status with project board | 1 day? | Mon 12.02.07 | Tue 13.02.07 | 71 | Executive Management,Information Systems,Accounting |
| Package integration design complete | 0 days | Tue 13.02.07 | Tue 13.02.07 | 72 | |
| Package Integration | 25 days? | Tue 13.02.07 | Mon 19.03.07 | | |
| Build Iteration Planning | 4 days? | Tue 13.02.07 | Fri 16.02.07 | | |
| Confirm technical architecture | 1 day? | Tue 13.02.07 | Wed 14.02.07 | 73 | Information Systems |
| Define iterations and builds | 1 day? | Wed 14.02.07 | Thu 15.02.07 | 76 | Information Systems |
| Refine test cases | 1 day? | Thu 15.02.07 | Fri 16.02.07 | 77 | Information Systems,Accounting |
| Integration Build | 5 days? | Fri 16.02.07 | Thu 22.02.07 | | |
| Build reports | 1 day? | Fri 16.02.07 | Mon 19.02.07 | 78 | Information Systems |
| Design and build migration components | 1 day? | Mon 19.02.07 | Tue 20.02.07 | 80 | Information Systems |
| Design and build external interfaces | 1 day? | Tue 20.02.07 | Wed 21.02.07 | 81 | Information Systems |
| Optimize performance | 1 day? | Tue 20.02.07 | Wed 21.02.07 | 81 | Information Systems |
| Complete unit/integration testing | 1 day? | Mon 19.02.07 | Tue 20.02.07 | | Information Systems |
| Review and baseline build | 1 day? | Tue 20.02.07 | Wed 21.02.07 | 84 | Information Systems |
| Deliver build for testing | 1 day? | Wed 21.02.07 | Thu 22.02.07 | 85 | Information Systems |
| System Test Design and Development | 3 days? | Thu 22.02.07 | Mon 26.02.07 | | |
| Define test scripts | 1 day? | Thu 22.02.07 | Fri 23.02.07 | 86 | Information Systems |
| Review test case/requirement coverage | 1 day? | Fri 23.02.07 | Mon 26.02.07 | 88 | Information Systems |
| Develop automated scripts | 1 day? | Thu 22.02.07 | Fri 23.02.07 | | Information Systems |
| Establish external test data sets | 1 day? | Fri 23.02.07 | Mon 26.02.07 | 88 | Information Systems |
| System Test Execution | 4 days? | Mon 26.02.07 | Thu 01.03.07 | | |
| Execute tests and log results | 1 day? | Mon 26.02.07 | Tue 27.02.07 | 91 | Information Systems |
| Investigate unexpected results | 1 day? | Tue 27.02.07 | Wed 28.02.07 | 93 | Information Systems |
| Estimate, prioritize, and schedule testing changes | 1 day? | Wed 28.02.07 | Thu 01.03.07 | 94 | Information Systems |
| Iteration Review | 3 days? | Thu 01.03.07 | Mon 05.03.07 | | |
| Review system test results for current iteration | 1 day? | Thu 01.03.07 | Fri 02.03.07 | 95 | Information Systems,Accounting |
| Confirm Scope of Future Iterations | 1 day? | Fri 02.03.07 | Mon 05.03.07 | 97 | Information Systems,Accounting |
| Acceptance Testing | 7 days? | Mon 05.03.07 | Tue 13.03.07 | | |
| Set up acceptance test environment | 1 day? | Mon 05.03.07 | Tue 06.03.07 | 98 | Information Systems |
| Create acceptance test scripts | 1 day? | Tue 06.03.07 | Wed 07.03.07 | 100 | Information Systems,Accounting |
| Execute acceptance tests and log results | 1 day? | Wed 07.03.07 | Thu 08.03.07 | 101 | Information Systems,Accounting |
| Update system based on acceptance test results | 1 day? | Thu 08.03.07 | Fri 09.03.07 | 102 | Information Systems,Accounting |
| Re-execute acceptance tests and log results | 1 day? | Fri 09.03.07 | Mon 12.03.07 | 103 | Information Systems,Accounting |
| Obtain signoff of system | 1 day? | Mon 12.03.07 | Tue 13.03.07 | 104 | Information Systems,Accounting |
| Package implementation complete | 0 days | Tue 13.03.07 | Tue 13.03.07 | 105 | |
| Finalize Package Integration Phase | 5 days? | Tue 13.03.07 | Mon 19.03.07 | | |
| Develop requirements traceability matrix | 1 day? | Tue 13.03.07 | Wed 14.03.07 | 106 | Information Systems,Accounting |
| Baseline project/deliverables | 1 day? | Wed 14.03.07 | Thu 15.03.07 | 108 | Information Systems,Accounting |
| Develop schedule for next stage | 1 day? | Thu 15.03.07 | Fri 16.03.07 | 109 | Information Systems,Accounting |
| Review project status with project board | 1 day? | Fri 16.03.07 | Mon 19.03.07 | 110 | |
| Package Deployment | 18 days? | Mon 19.03.07 | Wed 11.04.07 | | |
| Education Development | 5 days? | Mon 19.03.07 | Fri 23.03.07 | | |
| Set up training environment | 1 day? | Mon 19.03.07 | Tue 20.03.07 | 111 | Information Systems |
| Create application user guide | 1 day? | Tue 20.03.07 | Wed 21.03.07 | 114 | Information Systems,Accounting |
| Create administrators guide | 1 day? | Wed 21.03.07 | Thu 22.03.07 | 115 | Information Systems,Accounting |
| Develop training materials | 1 day? | Thu 22.03.07 | Fri 23.03.07 | 116 | Information Systems,Accounting |
| Package Deployment Preparation | 7 days? | Fri 23.03.07 | Mon 02.04.07 | | |
| Develop background scheduling processes | 1 day? | Fri 23.03.07 | Mon 26.03.07 | 117 | Information Systems |
| Create production test scripts | 1 day? | Mon 26.03.07 | Tue 27.03.07 | 119 | Information Systems |
| Review and compile technical implementation plan | 1 day? | Tue 27.03.07 | Wed 28.03.07 | 119,120 | Information Systems |
| Establish technical environment | 1 day? | Wed 28.03.07 | Thu 29.03.07 | 121 | Information Systems |
| Conduct deployment briefings | 1 day? | Thu 29.03.07 | Fri 30.03.07 | 122 | Information Systems |
| Conduct training | 1 day? | Fri 30.03.07 | Mon 02.04.07 | 123 | Accounting |
| Complete process review | 1 day? | Fri 30.03.07 | Mon 02.04.07 | 123 | |
| Installation and Handover | 6 days? | Mon 02.04.07 | Mon 09.04.07 | | |
| Install application software | 1 day? | Mon 02.04.07 | Tue 03.04.07 | 125 | Information Systems |
| Convert static and acquire new data | 1 day? | Tue 03.04.07 | Wed 04.04.07 | 127 | Information Systems |
| Convert dynamic data | 1 day? | Tue 03.04.07 | Wed 04.04.07 | 127 | Information Systems |
| Perform production tests | 1 day? | Wed 04.04.07 | Thu 05.04.07 | 128,129 | Information Systems |
| Cut over to new application | 1 day? | Thu 05.04.07 | Fri 06.04.07 | 130 | Information Systems |
| Create maintenance guide | 1 day? | Fri 06.04.07 | Mon 09.04.07 | 131 | |
| Finalize Deployment Phase | 3 days? | Mon 09.04.07 | Wed 11.04.07 | | |
| Perform lessons learned meeting | 1 day? | Mon 09.04.07 | Tue 10.04.07 | 132 | Information Systems,Accounting |
| Close project file | 1 day? | Tue 10.04.07 | Wed 11.04.07 | 134 | Information Systems,Accounting |
| Package deployment complete | 0 days | Wed 11.04.07 | Wed 11.04.07 | 135 | |
| Project complete | 0 days | Wed 11.04.07 | Wed 11.04.07 | 136 | |