| Electronic Government (E-Gov) Project | 13 days? | Mon 01.01.07 | Wed 17.01.07 | | |
| Program Management | 1 day? | Mon 01.01.07 | Mon 01.01.07 | | |
| Manage Ongoing Program Activities | 1 day? | Mon 01.01.07 | Mon 01.01.07 | | Program Management Office |
| Manage Progress Reporting | 1 day? | Mon 01.01.07 | Mon 01.01.07 | | Program Management Office |
| Support Data Consolidation | 1 day? | Mon 01.01.07 | Mon 01.01.07 | | Program Management Office |
| Perform Program Quality Assurance | 1 day? | Mon 01.01.07 | Mon 01.01.07 | | Program Management Office |
| Technical Architecture Support | 9 days? | Mon 01.01.07 | Thu 11.01.07 | | |
| Create Deployment Procedures | 1 day? | Mon 01.01.07 | Mon 01.01.07 | | IT Infrastructure Team |
| Create Security Procedures | 1 day? | Tue 02.01.07 | Tue 02.01.07 | 7 | IT Infrastructure Team |
| Create Web Portal Procedures | 1 day? | Wed 03.01.07 | Wed 03.01.07 | 8 | IT Infrastructure Team |
| Create Test/Development Environment | 1 day? | Thu 04.01.07 | Thu 04.01.07 | 9 | IT Infrastructure Team |
| Create Production Environment | 1 day? | Fri 05.01.07 | Fri 05.01.07 | 10 | IT Infrastructure Team |
| Create Change Control Procedures | 1 day? | Mon 08.01.07 | Mon 08.01.07 | 11 | IT Infrastructure Team |
| Create Client Support Procedures | 1 day? | Tue 09.01.07 | Tue 09.01.07 | 12 | IT Infrastructure Team |
| Communicate Procedures to Stakeholders | 1 day? | Wed 10.01.07 | Wed 10.01.07 | 13 | IT Infrastructure Team |
| Technical Architecture Complete | 1 day? | Thu 11.01.07 | Thu 11.01.07 | 14 | |
| Security Extranet | 11 days? | Wed 03.01.07 | Wed 17.01.07 | | |
| Analyze and Design Security Design | 1 day? | Wed 03.01.07 | Wed 03.01.07 | 8 | IT Cyber Security Team |
| Validate Security Requirements against Government Policies | 1 day? | Thu 04.01.07 | Thu 04.01.07 | 17 | IT Cyber Security Team |
| Create Security Tool RFP(s) | 1 day? | Fri 05.01.07 | Fri 05.01.07 | 18 | IT Cyber Security Team |
| Publish and Review Security Tool RFPs | 1 day? | Mon 08.01.07 | Mon 08.01.07 | 19 | IT Cyber Security Team |
| Select and Purchase Security Tool(s) | 1 day? | Tue 09.01.07 | Tue 09.01.07 | 20 | IT Cyber Security Team |
| Build Security Extranet Prototype | 1 day? | Wed 10.01.07 | Wed 10.01.07 | 21 | IT Cyber Security Team |
| Acceptance Test Security Prototype | 1 day? | Thu 11.01.07 | Thu 11.01.07 | 22 | IT Cyber Security Team |
| Create and Develop an Implementation Statement of Work | 1 day? | Fri 12.01.07 | Fri 12.01.07 | 23 | IT Cyber Security Team |
| Develop and Implement Security Extranet | 1 day? | Mon 15.01.07 | Mon 15.01.07 | 24 | IT Cyber Security Team |
| Final Acceptance Testing and Signoff | 1 day? | Tue 16.01.07 | Tue 16.01.07 | 25 | IT Cyber Security Team |
| Extranet Security Complete | 1 day? | Wed 17.01.07 | Wed 17.01.07 | 26 | |
| e-Payment Application Project | 13 days? | Mon 01.01.07 | Wed 17.01.07 | | |
| Project Initiation | 1 day? | Mon 01.01.07 | Mon 01.01.07 | | IT Applications Team |
| Analysis and Design | 1 day? | Tue 02.01.07 | Tue 02.01.07 | 29 | IT Applications Team |
| Initial Software Package Investigation | 1 day? | Wed 03.01.07 | Wed 03.01.07 | 30 | IT Applications Team |
| Software Package Evaluation | 1 day? | Thu 04.01.07 | Thu 04.01.07 | 31 | IT Applications Team |
| Final Package Selection | 1 day? | Fri 05.01.07 | Fri 05.01.07 | 32 | IT Applications Team |
| Implementation Services RFP Creation | 1 day? | Mon 08.01.07 | Mon 08.01.07 | 33 | IT Applications Team |
| Bidding Process and Vendor Selection | 1 day? | Tue 09.01.07 | Tue 09.01.07 | 34 | IT Applications Team |
| Implementation Vendor Award and Final Contracting | 1 day? | Wed 10.01.07 | Wed 10.01.07 | 35 | IT Applications Team |
| Software Installation and Configuration | 1 day? | Thu 11.01.07 | Thu 11.01.07 | 36 | IT Applications Team |
| User Acceptance Testing | 1 day? | Fri 12.01.07 | Fri 12.01.07 | 37 | IT Applications Team |
| Communications and Web Site Update Planning | 1 day? | Mon 15.01.07 | Mon 15.01.07 | 38 | IT Applications Team |
| Cut-Over - Final Implementation | 1 day? | Tue 16.01.07 | Tue 16.01.07 | 39 | IT Applications Team |
| e-Payment Project Complete | 1 day? | Wed 17.01.07 | Wed 17.01.07 | 40 | |
| E-Government Project Complete | 0 days | Wed 17.01.07 | Wed 17.01.07 | 15,26,41 | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |